Aseguramiento / Técnico
ACCEPTED_AS_EVIDENCE_EXECUTION_BASELINEFROZEN 2026-08-30T22:18:00ZVICTOR GUILLERMO DELGADO CESPEDES

This baseline is frozen for evidence acquisition and targeted blocker closure only. It does not authorize Phase 6B execution, Pilot exposure, or retrospective baseline reconstruction.

Phase 6A — Mesa 3 · Field Execution & Prospective Measurement Readiness

Does a real CV-07 workfront exist, is it operationally identifiable and executable, and can it be measured prospectively before any Pilot intervention alters the current way of working?

FIELD_EXECUTION_AND_MEASUREMENT_HOLDFIELD_AND_MEASUREMENT_DESIGN_STRUCTURALLY_SOUNDPILOT EXPOSURE PROHIBITEDBC-08BC-09

HOLD — OperationalClosureEvidence not yet sufficient. NOT DEMONSTRATED ≠ FAILED. No adverse field condition has been demonstrated.

ENTERPRISE_ENABLEMENT_HOLD — BC-01/02/03/05/06 REMAINS_OPEN, EvidenceQuality NONE, RetestEligibility 0/5. External; not reopened, not closed, not simulated.

ORGANIZATIONAL_GOVERNANCE_HOLD — BC-04/BC-07 REMAINS_OPEN (evidence acquisition required), GOVERNANCE_DESIGN_STRUCTURALLY_SOUND, retest NOT YET ELIGIBLE. External; untouched.

  • BC-08 and BC-09 are evaluated together: no real workfront means no valid field baseline, and Pilot exposure before BEFORE capture permanently compromises causal attribution.
  • NO PILOT INTERVENTION MAY ALTER THE CURRENT WAY OF WORKING BEFORE PROSPECTIVE BEFORE MEASUREMENT HAS FORMALLY COMMENCED.
  • ADR-14 preserved: Location is an Operational Context Container, never a WorkPackage; one Location may hold multiple concurrent JobCards and disciplines.
  • Non-compensable: one mandatory unresolved condition means READY is NOT PERMITTED — no weighted aggregate exists.
  • External dependency on Mesa 1 or Mesa 2 is recorded as DEPENDENCY_HELD, never as a Mesa 3 field failure.
  • Readiness to measure is not authorization to Pilot; Mesa 3 proves field and measurement readiness only.
  • No Mesa 1 / Mesa 2 reopening or closure. No Phase 6A integrated revalidation. No Phase 6B execution.
  • No Pilot functionality exposed to field users. No BEFORE contamination. No retrospective BEFORE reconstruction.
  • No simulated field readiness, no simulated Critical Control participation, no BC-06 Path A/B election (Mesa 1 authority).
  • No invented JobCards, Locations, metrics, source participation or numeric improvement targets.
  • No architecture change and no change to frozen Pilot scope without formal authority.

· How to read this HOLD

  • OPEN / EVIDENCE_REQUIRED → amber. STRUCTURALLY_SOUND → controlled positive. HOLD → controlled warning. PROHIBITED / CONTAMINATED / CONTRADICTED / FAIL → red. Missing evidence alone never renders red.
  • Mesa 1 and Mesa 2 conditions are recorded as external dependencies (DEPENDENCY_HELD), not as Mesa 3 failures.
  • The Mesa 3 field readiness model, measurement event model, attribution rule and anti-contamination controls have no identified structural contradiction. This does not imply READY, CLOSED, baseline started or Phase 6A GO.
  • Absence of evidence is not a confirmed failure. 0 criteria are confirmed failed based on the current evidence set.

A · Executive field & measurement readiness summary

Disposition

FIELD_EXECUTION_AND_MEASUREMENT_HOLD

Field & Measurement Design Condition

FIELD_AND_MEASUREMENT_DESIGN_STRUCTURALLY_SOUND

BC-08

REMAINS_OPEN — Evidence acquisition required

BC-09

REMAINS_OPEN — Prospective BEFORE collection has not formally commenced

Operational Closure Evidence

NOT_YET_SUFFICIENT

Prospective Baseline

NOT_STARTED

Pilot Exposure

PROHIBITED — BC09Protection = ACTIVE

Contamination

NO BC09_CONTAMINATION_EVENT RECORDED

Structural Contradiction

NONE IDENTIFIED

Retest Eligibility

NOT YET ELIGIBLE

Required distinction: these four are not equivalent.

  • Field design sound — YES (model, registers and failure behaviour defined; DesignEvidence only).
  • Field evidence sufficient — NO (no confirmed field prerequisite carries operational evidence).
  • Prospective baseline started — NO (0 of 12 metrics are COLLECTING; measurement has not commenced).
  • Pilot authorized — NO (Phase 6A HOLD; Mesa 1 and Mesa 2 blockers open; Phase 6B not commenced).
  • A candidate CV-07 workfront is described in design and prototype scenario terms, but no field-verified WorkPackage / JobCard set, crew assignment or planned execution window has been supplied by a competent field owner.
  • Canonical Location identity remains DEPENDENCY_HELD under Mesa 1 (ADR-14 federated canonical Location register unconfirmed); physical location context can be described, but governed identity cannot be evidenced.
  • Work demand existence and lifecycle authority are deliberately separated: even where demand can be shown, lifecycle authority is unresolved under BC-03 and cannot be inferred from the presence of a JobCard.
  • SIMOPS field context cannot be established from real concurrent-work records; the pairwise-versus-location distinction is preserved in model form only.
  • Critical Control field participation is HELD_BY_MESA_1 pending the BC-06 Path A / Path B decision; Mesa 3 neither elects nor simulates it.
  • All 12 frozen BEFORE metrics remain at DEFINED; none has a confirmed source owner, validated timestamp basis or commenced collection, so BC-09 cannot close on design readiness alone.
  • No contamination event has occurred because no Pilot capability has been exposed; the anti-contamination register defaults every material workflow change to NOT ALLOWED before baseline.

B · BC-08 CV-07 field scope definition

Field scope is recorded only to the extent evidence exists. Every unevidenced attribute is NOT_YET_AVAILABLE and is never inferred, defaulted or fabricated.

Location = Operational Context Container. Location ≠ WorkPackage. One Location may contain multiple concurrent JobCards across disciplines.

Project_IDSUPPORTED

Value: CV-07 Pilot corridor (frozen Phase 6 Pilot scope)

Source: Phase 6 Pilot Definition Baseline (frozen)

AreaSUPPORTED

Value: Concentrator — material handling

Source: Phase 6 Pilot Definition Baseline

SectorNOT_YET_AVAILABLE

Value: NOT_YET_AVAILABLE — field sector designation not supplied by Construction

Source: Construction Management (pending)

FacilityINCONCLUSIVE

Value: Transfer Tower 01 (candidate, unverified in field)

Source: Prototype scenario — not field-verified

SystemSUPPORTED

Value: Conveying / transfer system CV-07

Source: Phase 6 Pilot Definition Baseline

SubsystemNOT_YET_AVAILABLE

Value: NOT_YET_AVAILABLE — subsystem breakdown not confirmed against commissioning register

Source: Commissioning (pending)

WorkLocationINCONCLUSIVE

Value: Candidate workfront at transfer tower level +12 m; physical verification not performed

Source: Field verification required

CanonicalLocationRefNOT_YET_AVAILABLE

Value: DEPENDENCY_HELD — federated canonical Location register unconfirmed (Mesa 1 / ADR-14 Option C)

Source: Mesa 1 BC-01 / ADR-14 stewardship

OperationalLocationRefNOT_YET_AVAILABLE

Value: NOT_YET_AVAILABLE — operational location reference not issued by Location steward

Source: Location steward (vacant — Mesa 2 BC-04)

WorkPackage_IDNOT_YET_AVAILABLE

Value: NOT_YET_AVAILABLE — no field-confirmed work package identifier released for Pilot window

Source: Work Control / Q4 (BC-01)

JobCard_IDNOT_YET_AVAILABLE

Value: NOT_YET_AVAILABLE — JobCards must not be fabricated to enable Pilot execution

Source: Work Control / Q4 (BC-01, BC-03)

DisciplineINCONCLUSIVE

Value: Mechanical / Electrical / Instrumentation expected; actual discipline mix unconfirmed

Source: Construction planning (pending)

CrewNOT_YET_AVAILABLE

Value: NOT_YET_AVAILABLE — crew rosters not supplied

Source: Construction / Contractor supervision

ShiftNOT_YET_AVAILABLE

Value: NOT_YET_AVAILABLE — shift pattern for Pilot window not confirmed

Source: Construction planning

PlannedExecutionWindowNOT_YET_AVAILABLE

Value: NOT_YET_AVAILABLE — no planned window issued; Pilot execution remains on HOLD

Source: P6 schedule (BC-01)

ActualExecutionWindowNOT_YET_AVAILABLE

Value: NOT_APPLICABLE_YET — no execution has occurred

Source: n/a

SupervisorNOT_YET_AVAILABLE

Value: NOT_YET_AVAILABLE — named field supervisor not nominated

Source: Construction (Mesa 2 dependency)

FieldOwnerNOT_YET_AVAILABLE

Value: NOT_YET_AVAILABLE — accountable field owner for the Pilot workfront not nominated

Source: Construction Management

SourceEvidenceNOT_YET_AVAILABLE

Value: DesignEvidence only. No operational field record has been received.

Source: Mesa 3 evidence queue

C · Field prerequisite register (BC-08)

NOT_YET_AVAILABLE is never converted into FAIL. It records absent evidence, not a demonstrated adverse condition. A single unresolved non-compensable prerequisite makes READY NOT PERMITTED regardless of how many others are satisfied.

FP-01 · LocationNOT_YET_AVAILABLENON-COMPENSABLEFIELD VERIFICATION

Condition: A real, identifiable and governed WorkLocation exists for the CV-07 workfront

Authoritative source: Federated canonical Location register (ADR-14 Option C)

Competent owner: Location Steward

Required by: Before any readiness decision

Evidence ref:

Validity basis: Steward-issued canonical reference with effective date

Dependency: BC-01 (participation), BC-04 (stewardship)

Disposition: DEPENDENCY_HELD — not a field failure

FP-02 · WorkPackage / JobCardNOT_YET_AVAILABLENON-COMPENSABLEFIELD VERIFICATION

Condition: Real work demand exists with identifiable WorkPackage and JobCards

Authoritative source: Work control system of record

Competent owner: Work Control Lead

Required by: Before Pilot field execution

Evidence ref:

Validity basis: Extract from authoritative work-control record for the Pilot window

Dependency: BC-01, BC-03

Disposition: REMAINS_OPEN — evidence acquisition required

FP-03 · EngineeringNOT_YET_AVAILABLENON-COMPENSABLE

Condition: Applicable released engineering (drawings, specifications) exists at pinned versions

Authoritative source: Document management system of record

Competent owner: Engineering Document Controller

Required by: Package preparation

Evidence ref:

Validity basis: Version-pinned document reference with revision and status

Dependency: BC-01

Disposition: REMAINS_OPEN

FP-04 · MaterialsNOT_YET_AVAILABLENON-COMPENSABLEFIELD VERIFICATION

Condition: Required materials are identified, available and released to the workfront

Authoritative source: Materials management record

Competent owner: Materials / Warehouse Lead

Required by: Before mobilisation

Evidence ref:

Validity basis: Reservation/issue record against the work package

Dependency: BC-01

Disposition: REMAINS_OPEN

FP-05 · BEO / EquipmentNOT_YET_AVAILABLENON-COMPENSABLEFIELD VERIFICATION

Condition: Required construction equipment is available, certified and allocated

Authoritative source: Equipment register / certification record

Competent owner: Construction Equipment Lead

Required by: Before mobilisation

Evidence ref:

Validity basis: Certification validity dates within execution window

Dependency:

Disposition: REMAINS_OPEN

FP-06 · ToolsNOT_YET_AVAILABLEFIELD VERIFICATION

Condition: Required tooling, including special tooling, is available and inspection-valid

Authoritative source: Tool control / inspection record

Competent owner: Site Tool Controller

Required by: Before mobilisation

Evidence ref:

Validity basis: Inspection tag validity

Dependency:

Disposition: REMAINS_OPEN

FP-07 · WorkforceNOT_YET_AVAILABLENON-COMPENSABLEFIELD VERIFICATION

Condition: Crew composition and headcount for the planned window are known and assigned

Authoritative source: Contractor roster

Competent owner: Contractor Superintendent

Required by: Before planning lock

Evidence ref:

Validity basis: Roster valid for the specific shift and window

Dependency: BC-02 (identity)

Disposition: REMAINS_OPEN

FP-08 · Competency / TrainingNOT_YET_AVAILABLENON-COMPENSABLE

Condition: Each assigned worker holds valid, in-date competency for the assigned task

Authoritative source: Competency system of record

Competent owner: Training & Competency Lead

Required by: Before task assignment

Evidence ref:

Validity basis: Competency expiry after planned execution end

Dependency: BC-01, BC-02, BC-05 (data minimisation)

Disposition: REMAINS_OPEN

FP-09 · Fitness / HabilitationNOT_YET_AVAILABLENON-COMPENSABLE

Condition: Medical fitness / habilitation status valid for the task and location

Authoritative source: Occupational health record (minimised: status only)

Competent owner: Occupational Health

Required by: Before task assignment

Evidence ref:

Validity basis: Status flag with validity date; no clinical data transferred

Dependency: BC-05

Disposition: REMAINS_OPEN — data minimisation constraint applies

FP-10 · Construction AreaNOT_YET_AVAILABLENON-COMPENSABLEFIELD VERIFICATION

Condition: Area is physically accessible, prepared and released for the planned work

Authoritative source: Area release / access control record

Competent owner: Area Construction Superintendent

Required by: Before mobilisation

Evidence ref:

Validity basis: Signed area release valid for the window

Dependency:

Disposition: REMAINS_OPEN

FP-11 · EnvironmentNOT_YET_AVAILABLENON-COMPENSABLEFIELD VERIFICATION

Condition: Environmental conditions (wind, storm, heat, dust, visibility) within operating limits at execution

Authoritative source: Site meteorological / environmental monitoring

Competent owner: ES&H Lead

Required by: At execution, continuously

Evidence ref:

Validity basis: Reading timestamp within the validity window of the decision

Dependency: BC-01

Disposition: REMAINS_OPEN

FP-12 · Client / Owner ReleaseNOT_YET_AVAILABLENON-COMPENSABLE

Condition: Client or owner release exists where the system or area is under owner control

Authoritative source: Owner release register

Competent owner: Client Interface Manager

Required by: Before entering owner-controlled scope

Evidence ref:

Validity basis: Release document with scope and validity

Dependency:

Disposition: REMAINS_OPEN

FP-13 · Logistics / TransportNOT_YET_AVAILABLEFIELD VERIFICATION

Condition: Transport, lifting and delivery logistics to the workfront are arranged

Authoritative source: Logistics plan

Competent owner: Site Logistics Coordinator

Required by: Before mobilisation

Evidence ref:

Validity basis: Booking confirmation for the window

Dependency:

Disposition: REMAINS_OPEN

FP-14 · SIMOPS / InterfacesNOT_YET_AVAILABLENON-COMPENSABLEFIELD VERIFICATION

Condition: Concurrent work at the Location is known and cumulatively evaluated (CUM-1…CUM-7)

Authoritative source: Location concurrent work set (federated)

Competent owner: ES&H / SIMOPS Coordinator

Required by: Before authorization and at execution

Evidence ref:

Validity basis: Concurrent set complete for the Location and time overlap

Dependency: BC-01, BC-04

Disposition: REMAINS_OPEN — completeness of the concurrent set cannot be evidenced

FP-15 · Operational RestrictionsNOT_YET_AVAILABLENON-COMPENSABLEFIELD VERIFICATION

Condition: Active operational restrictions, exclusion zones and temporary modifications are known

Authoritative source: Restriction / temporary modification register (ADR-17)

Competent owner: Operations Interface Lead

Required by: Before authorization

Evidence ref:

Validity basis: Register current at decision time

Dependency: BC-03 (ADR-17 lifecycle authority)

Disposition: REMAINS_OPEN

FP-16 · Emergency / Response ConditionsNOT_YET_AVAILABLENON-COMPENSABLEFIELD VERIFICATION

Condition: Emergency response, rescue and evacuation provisions valid for the workfront

Authoritative source: Emergency response plan / ES&H record

Competent owner: Emergency Response Coordinator

Required by: Before execution

Evidence ref:

Validity basis: Plan applicable to the location, task and shift

Dependency:

Disposition: REMAINS_OPEN

FP-17 · Critical Control ParticipationNOT_YET_AVAILABLENON-COMPENSABLEFIELD VERIFICATION

Condition: Critical Control verification participation exists for activities exposed to critical risk

Authoritative source: Critical control system (unelected — BC-06 Path A/B)

Competent owner: Critical Risk Owner (Mesa 1 authority)

Required by: Before execution of critical-risk activity

Evidence ref:

Validity basis: Real verification record; simulation is inadmissible

Dependency: BC-06

Disposition: CriticalControlFieldDependency = HELD_BY_MESA_1

D · Location validation

GPS may support physical context. GPS must not become canonical identity authority. Where canonical/federated identity remains unresolved under Mesa 1, record DEPENDENCY_HELD, not FIELD_FAIL.

Physical location exists and is reachableINCONCLUSIVE

Basis: Candidate workfront described; no field walk-down record received.

Governed Location reference (canonical)NOT_YET_AVAILABLE

Basis: DEPENDENCY_HELD — federated canonical Location register unconfirmed (ADR-14 Option C, Mesa 1).

Operational location reference where applicableNOT_YET_AVAILABLE

Basis: No steward-issued operational reference; Location steward unassigned (Mesa 2).

Boundaries definedNOT_YET_AVAILABLE

Basis: Boundary definition requires steward issuance and field confirmation.

Access conditionsNOT_YET_AVAILABLE

Basis: Access control record not supplied.

Active work at the LocationNOT_YET_AVAILABLE

Basis: No concurrent work extract received; cannot be inferred.

Planned work at the LocationNOT_YET_AVAILABLE

Basis: Schedule participation unresolved (BC-01).

Equipment presentNOT_YET_AVAILABLE

Basis: Field inventory not performed.

Restrictions in forceNOT_YET_AVAILABLE

Basis: Restriction register participation unresolved.

Environmental conditionsNOT_YET_AVAILABLE

Basis: Monitoring feed not connected; wind limit logic exists as design only.

Simultaneous work identifiedNOT_YET_AVAILABLE

Basis: See SIMOPS field context; completeness unprovable today.

Relevant lessons / operational contextNOT_YET_AVAILABLE

Basis: Lessons source not nominated.

LOCATION_FIELD_VALIDATION = NOT_DEMONSTRATED (DEPENDENCY_HELD on Mesa 1 for canonical identity). No FIELD_FAIL is recorded.

E · Work demand validation

Do not fabricate JobCards to make Pilot execution possible. WorkDemandExists and LifecycleAuthorityResolved are separate determinations.

WorkDemandExists

NOT_DEMONSTRATED — no authoritative work-control extract for the Pilot window has been received.

LifecycleAuthorityResolved

NO — ADR-15 (JobCard) and ADR-17 (TemporaryModification) transition authority unresolved under Mesa 1 / BC-03.

Even if a WorkPackage extract arrives and demonstrates real demand, BC-08 cannot be closed on that alone while lifecycle authority remains unresolved; conversely, resolved lifecycle authority never substitutes for the absence of real demand.

WorkPackageNOT_YET_AVAILABLE

Note: Authoritative identifier required from Work Control.

JobCardNOT_YET_AVAILABLE

Note: Must originate in the system of record; fabrication prohibited.

DisciplineINCONCLUSIVE

Note: Multi-discipline expected at one Location (ADR-14 container behaviour).

ScopeNOT_YET_AVAILABLE

Note: Scope statement per JobCard required.

PlannedStartNOT_YET_AVAILABLE

Note: Schedule participation unresolved (BC-01).

PlannedFinishNOT_YET_AVAILABLE

Note: As above.

CrewNOT_YET_AVAILABLE

Note: Roster not supplied.

EquipmentNOT_YET_AVAILABLE

Note: Allocation record not supplied.

RequiredControlsNOT_YET_AVAILABLE

Note: Control set derives from applicability rules whose governance is unresolved.

LocationNOT_YET_AVAILABLE

Note: DEPENDENCY_HELD (canonical reference).

ScheduleReferenceNOT_YET_AVAILABLE

Note: P6 activity ID linkage not evidenced.

F · SIMOPS field context

Pairwise PASS ≠ Location PASS. ActivityRisk, LocationRisk and SIMOPSInteractionRisk are evaluated separately and never merged into one score. SIMOPS evidence is never invented.

LocationConcurrentWorkSetNOT_ESTABLISHED

Basis: LocationConcurrentWorkSet for CV-07 cannot be constructed: no authoritative concurrent-work extract exists for the Location and time window. Completeness of the set is itself a non-compensable condition — an incomplete set cannot be evaluated as safe.

ActiveJob: NOT_YET_AVAILABLEPlannedJob: NOT_YET_AVAILABLEDiscipline: INCONCLUSIVETimeOverlap: NOT_YET_AVAILABLEEnergyInteraction: NOT_YET_AVAILABLEIsolationInteraction: NOT_YET_AVAILABLEAccessInteraction: NOT_YET_AVAILABLEEquipmentInteraction: NOT_YET_AVAILABLEExclusionZoneInteraction: NOT_YET_AVAILABLECriticalRiskInteraction: NOT_YET_AVAILABLEEnvironmentInteraction: NOT_YET_AVAILABLEPermitInteraction: NOT_YET_AVAILABLE
ActivityRisk

Meaning: Risk of the individual activity in isolation.

State: Model defined (DesignEvidence); no field data.

LocationRisk

Meaning: Cumulative risk of the Location as an operational container, independent of any single activity.

State: Model defined; no field data.

SIMOPSInteractionRisk

Meaning: Risk arising from interaction between concurrent activities (CUM-1…CUM-7).

State: Model defined; no field data.

SIMOPS_FIELD_CONTEXT = NOT_ESTABLISHED — evidence acquisition required. No adverse SIMOPS condition is asserted.

G · Critical Control field dependency

Mesa 3 shall not create or elect BC-06 Path A / Path B. That decision remains Mesa 1 authority. Real critical-control participation is never simulated.

CriticalControlFieldDependency = HELD_BY_MESA_1
Do relevant Critical Risks exist in CV-07?

Finding: PLAUSIBLE — the corridor involves stored/mechanical energy, working at height, lifting and isolation interfaces. Definitive determination requires the Critical Risk Owner, who is not yet nominated.

Which field activities would require Critical Control participation?

Finding: Isolation and energy-state changes, lifting operations, work at height at the transfer tower, and any confined or restricted access task within the Location container.

Would actual field verification be required?

Finding: YES — where a critical control applies, verification is a field act with an attributable verifier; a system flag is not verification.

What evidence would need to exist for Pilot execution?

Finding: A named critical risk owner, an elected Path A source of verification records (or a formally recorded Path B rescope), verifier identity through real IAM (BC-02), and a verification record retrievable for evidence reconstruction.

No simulated verification record may be produced, displayed or counted in Mesa 3.

H · Field user / supervision readiness

Prototype role labels are not actual field assignments. No person is treated as a Pilot participant without an evidenced nomination; authority dependencies (Mesa 1) and organizational assignment dependencies (Mesa 2) are recorded explicitly rather than absorbed.

Field Supervisor (Mechanical)NOT_CONFIRMED

Actual availability: NOT_YET_AVAILABLE

Shift: NOT_YET_AVAILABLE

Training status: NOT_DELIVERED (delivery would be a contamination risk — see anti-contamination register)

Current workflow: Existing paper/hybrid preparation workflow (to be characterised by passive observation)

Evidence ref:

Dependency: Mesa 2 (assignment), Mesa 1 BC-02 (identity)

SuperintendentNOT_CONFIRMED

Actual availability: NOT_YET_AVAILABLE

Shift: NOT_YET_AVAILABLE

Training status: NOT_DELIVERED

Current workflow: Existing shift planning routine

Evidence ref:

Dependency: Mesa 2

ForemanNOT_CONFIRMED

Actual availability: NOT_YET_AVAILABLE

Shift: NOT_YET_AVAILABLE

Training status: NOT_DELIVERED

Current workflow: Existing crew briefing routine

Evidence ref:

Dependency: Mesa 2

CrewNOT_CONFIRMED

Actual availability: NOT_YET_AVAILABLE

Shift: NOT_YET_AVAILABLE

Training status: NOT_DELIVERED

Current workflow: Existing task execution routine

Evidence ref:

Dependency: Mesa 1 BC-02, BC-05

ES&HNOT_CONFIRMED

Actual availability: NOT_YET_AVAILABLE

Shift: NOT_YET_AVAILABLE

Training status: NOT_DELIVERED

Current workflow: Existing SIMOPS coordination routine

Evidence ref:

Dependency: Mesa 2 BC-04

Field SupportNOT_CONFIRMED

Actual availability: NOT_YET_AVAILABLE

Shift: NOT_YET_AVAILABLE

Training status: NOT_DELIVERED

Current workflow: None — design team is currently de-facto support

Evidence ref:

Dependency: Mesa 2 BC-07

Construction (Area)NOT_CONFIRMED

Actual availability: NOT_YET_AVAILABLE

Shift: NOT_YET_AVAILABLE

Training status: NOT_DELIVERED

Current workflow: Existing area release routine

Evidence ref:

Dependency: Mesa 2

Operational authority (owner interface)NOT_CONFIRMED

Actual availability: NOT_YET_AVAILABLE

Shift: NOT_YET_AVAILABLE

Training status: NOT_DELIVERED

Current workflow: Existing owner release routine

Evidence ref:

Dependency: Mesa 1 BC-03, Mesa 2 BC-04

I · 12-metric prospective BEFORE baseline register (BC-09)

The frozen 12-metric Pilot baseline structure is preserved, not replaced or reinterpreted. No numeric target or expected improvement is stated. No metric is labelled COLLECTING because collection has not commenced. Status is evidence-driven: all 12 remain DEFINED.

DEFINED: 12SOURCE_CONFIRMED: 0OWNER_CONFIRMED: 0COLLECTION_READY: 0COLLECTING: 0INSUFFICIENT_DATA: 0BASELINE_ESTABLISHED: 0
M-01 · PackagePreparationTimeDEFINEDhours per work package

Operational definition: Elapsed working time from work package initiation to supervisor-declared prepared, for packages in the CV-07 field scope.

Measurement window: PackageInitiated → PreparedDeclared

Source: Work control record (authoritative)

Collection method: Event extract with supervisor confirmation

Owner: NOT_YET_CONFIRMED — measurement owner nomination pending

Frequency: Per package

Timestamp basis: System event timestamp, site timezone, clock source to be validated

Exclusions: Packages outside CV-07 scope; packages cancelled before preparation.

Correction rule: Corrections permitted only with recorded reason, corrector identity and timestamp; original value retained and never overwritten.

Missing data rule: Missing values are recorded as MISSING with reason; they are never imputed, averaged or back-filled.

Concurrent constraint rule: Where more than one constraint is active in the same interval, apply the concurrent constraint attribution model (Section K); never double-count time or value.

Attribution rule: Attribution recorded as PRIMARY / CONTRIBUTORY / CONCURRENT / SHARED_CAUSATION / UNATTRIBUTED per governed rule; false precision prohibited.

Evidence ref:

M-02 · ApprovalLatencyDEFINEDhours

Operational definition: Elapsed time between submission for authorization and the authorization decision.

Measurement window: Submitted → Approved

Source: Work control transaction log

Collection method: Event extract

Owner: NOT_YET_CONFIRMED — measurement owner nomination pending

Frequency: Per submission

Timestamp basis: Transaction log timestamp; clock reliability unvalidated

Exclusions: Submissions withdrawn by the originator before review.

Correction rule: Corrections permitted only with recorded reason, corrector identity and timestamp; original value retained and never overwritten.

Missing data rule: Missing values are recorded as MISSING with reason; they are never imputed, averaged or back-filled.

Concurrent constraint rule: Where more than one constraint is active in the same interval, apply the concurrent constraint attribution model (Section K); never double-count time or value.

Attribution rule: Attribution recorded as PRIMARY / CONTRIBUTORY / CONCURRENT / SHARED_CAUSATION / UNATTRIBUTED per governed rule; false precision prohibited.

Evidence ref:

M-03 · RestrictionDetectionLeadTimeDEFINEDhours before planned start

Operational definition: Time between a restriction becoming knowable and it being recorded against the package.

Measurement window: RestrictionKnowable → RestrictionRecorded

Source: Restriction register + supervisor log

Collection method: Prospective log entry at time of detection (no retrospective reconstruction)

Owner: NOT_YET_CONFIRMED — measurement owner nomination pending

Frequency: Per restriction

Timestamp basis: Manual log timestamp; requires observer discipline

Exclusions: Restrictions raised outside the CV-07 Location container.

Correction rule: Corrections permitted only with recorded reason, corrector identity and timestamp; original value retained and never overwritten.

Missing data rule: Missing values are recorded as MISSING with reason; they are never imputed, averaged or back-filled.

Concurrent constraint rule: Where more than one constraint is active in the same interval, apply the concurrent constraint attribution model (Section K); never double-count time or value.

Attribution rule: Attribution recorded as PRIMARY / CONTRIBUTORY / CONCURRENT / SHARED_CAUSATION / UNATTRIBUTED per governed rule; false precision prohibited.

Evidence ref:

M-04 · BlockerResolutionTimeDEFINEDhours per blocker

Operational definition: Time from blocker raised to blocker closed, recorded by blocker type and accountable owner.

Measurement window: BlockerRaised → BlockerClosed

Source: Supervisor log / work control

Collection method: Prospective log

Owner: NOT_YET_CONFIRMED — measurement owner nomination pending

Frequency: Per blocker

Timestamp basis: Log timestamp

Exclusions: Blockers not affecting CV-07 scope work.

Correction rule: Corrections permitted only with recorded reason, corrector identity and timestamp; original value retained and never overwritten.

Missing data rule: Missing values are recorded as MISSING with reason; they are never imputed, averaged or back-filled.

Concurrent constraint rule: Where more than one constraint is active in the same interval, apply the concurrent constraint attribution model (Section K); never double-count time or value.

Attribution rule: Attribution recorded as PRIMARY / CONTRIBUTORY / CONCURRENT / SHARED_CAUSATION / UNATTRIBUTED per governed rule; false precision prohibited.

Evidence ref:

M-05 · ReworkDEFINEDcount and hours per period

Operational definition: Preparation activities repeated because of defective or superseded preparation. Construction rework is explicitly excluded.

Measurement window: ReworkTriggered → ReworkCompleted

Source: Supervisor log

Collection method: Prospective log with cause code

Owner: NOT_YET_CONFIRMED — measurement owner nomination pending

Frequency: Per occurrence

Timestamp basis: Log timestamp

Exclusions: Construction/physical rework; scope-change-driven repreparation recorded separately.

Correction rule: Corrections permitted only with recorded reason, corrector identity and timestamp; original value retained and never overwritten.

Missing data rule: Missing values are recorded as MISSING with reason; they are never imputed, averaged or back-filled.

Concurrent constraint rule: Where more than one constraint is active in the same interval, apply the concurrent constraint attribution model (Section K); never double-count time or value.

Attribution rule: Attribution recorded as PRIMARY / CONTRIBUTORY / CONCURRENT / SHARED_CAUSATION / UNATTRIBUTED per governed rule; false precision prohibited.

Evidence ref:

M-06 · DuplicateDataEntryDEFINEDentries per package

Operational definition: Count of occurrences where the same datum is entered into more than one system during preparation.

Measurement window: ObservationSessionStart → ObservationSessionEnd

Source: Structured passive observation study

Collection method: Observer tally sheet (non-intrusive; observer does not advise or prompt)

Owner: NOT_YET_CONFIRMED — measurement owner nomination pending

Frequency: Per observed session

Timestamp basis: Observer clock, synchronised to site time

Exclusions: Entries made for training or testing purposes.

Correction rule: Corrections permitted only with recorded reason, corrector identity and timestamp; original value retained and never overwritten.

Missing data rule: Missing values are recorded as MISSING with reason; they are never imputed, averaged or back-filled.

Concurrent constraint rule: Where more than one constraint is active in the same interval, apply the concurrent constraint attribution model (Section K); never double-count time or value.

Attribution rule: Attribution recorded as PRIMARY / CONTRIBUTORY / CONCURRENT / SHARED_CAUSATION / UNATTRIBUTED per governed rule; false precision prohibited.

Evidence ref:

M-07 · DocumentSearchEffortDEFINEDminutes per package

Operational definition: Time spent locating a document and confirming its version validity during preparation.

Measurement window: SearchStart → VersionConfirmed

Source: Passive observation study

Collection method: Timed observation

Owner: NOT_YET_CONFIRMED — measurement owner nomination pending

Frequency: Per observed session

Timestamp basis: Observer clock

Exclusions: Searches unrelated to the observed package.

Correction rule: Corrections permitted only with recorded reason, corrector identity and timestamp; original value retained and never overwritten.

Missing data rule: Missing values are recorded as MISSING with reason; they are never imputed, averaged or back-filled.

Concurrent constraint rule: Where more than one constraint is active in the same interval, apply the concurrent constraint attribution model (Section K); never double-count time or value.

Attribution rule: Attribution recorded as PRIMARY / CONTRIBUTORY / CONCURRENT / SHARED_CAUSATION / UNATTRIBUTED per governed rule; false precision prohibited.

Evidence ref:

M-08 · FieldClarificationRequestsDEFINEDcount per shift

Operational definition: Count of field-to-office clarification contacts arising from preparation ambiguity.

Measurement window: ClarificationRaised → ClarificationAnswered

Source: Shift log

Collection method: Prospective log

Owner: NOT_YET_CONFIRMED — measurement owner nomination pending

Frequency: Per shift

Timestamp basis: Shift log timestamp

Exclusions: Commercial or HR queries.

Correction rule: Corrections permitted only with recorded reason, corrector identity and timestamp; original value retained and never overwritten.

Missing data rule: Missing values are recorded as MISSING with reason; they are never imputed, averaged or back-filled.

Concurrent constraint rule: Where more than one constraint is active in the same interval, apply the concurrent constraint attribution model (Section K); never double-count time or value.

Attribution rule: Attribution recorded as PRIMARY / CONTRIBUTORY / CONCURRENT / SHARED_CAUSATION / UNATTRIBUTED per governed rule; false precision prohibited.

Evidence ref:

M-09 · LateSIMOPSDetectionDEFINEDcount and hours before start

Operational definition: SIMOPS interactions first identified at or after mobilisation rather than during planning.

Measurement window: InteractionExists → InteractionIdentified

Source: ES&H / shift records

Collection method: Prospective log

Owner: NOT_YET_CONFIRMED — measurement owner nomination pending

Frequency: Per occurrence

Timestamp basis: Record timestamp

Exclusions: Interactions outside the CV-07 Location container.

Correction rule: Corrections permitted only with recorded reason, corrector identity and timestamp; original value retained and never overwritten.

Missing data rule: Missing values are recorded as MISSING with reason; they are never imputed, averaged or back-filled.

Concurrent constraint rule: Where more than one constraint is active in the same interval, apply the concurrent constraint attribution model (Section K); never double-count time or value.

Attribution rule: Attribution recorded as PRIMARY / CONTRIBUTORY / CONCURRENT / SHARED_CAUSATION / UNATTRIBUTED per governed rule; false precision prohibited.

Evidence ref:

M-10 · WorkStartDelayDEFINEDminutes after planned start

Operational definition: Difference between planned and actual start at the workface, with primary delay cause recorded at the time of occurrence.

Measurement window: PlannedStart → WorkStarted

Source: Field supervision record

Collection method: Prospective log with cause code

Owner: NOT_YET_CONFIRMED — measurement owner nomination pending

Frequency: Per job card start

Timestamp basis: Supervisor record; workface clock

Exclusions: Starts cancelled before mobilisation.

Correction rule: Corrections permitted only with recorded reason, corrector identity and timestamp; original value retained and never overwritten.

Missing data rule: Missing values are recorded as MISSING with reason; they are never imputed, averaged or back-filled.

Concurrent constraint rule: Where more than one constraint is active in the same interval, apply the concurrent constraint attribution model (Section K); never double-count time or value.

Attribution rule: Attribution recorded as PRIMARY / CONTRIBUTORY / CONCURRENT / SHARED_CAUSATION / UNATTRIBUTED per governed rule; false precision prohibited.

Evidence ref:

M-11 · ReadinessFirstPassDEFINED% of packages

Operational definition: Proportion of packages authorized on first submission without returned rework.

Measurement window: Submitted → Approved or Returned

Source: Work control transaction log

Collection method: Event extract

Owner: NOT_YET_CONFIRMED — measurement owner nomination pending

Frequency: Per period

Timestamp basis: Transaction log

Exclusions: Administrative resubmissions with no content change.

Correction rule: Corrections permitted only with recorded reason, corrector identity and timestamp; original value retained and never overwritten.

Missing data rule: Missing values are recorded as MISSING with reason; they are never imputed, averaged or back-filled.

Concurrent constraint rule: Where more than one constraint is active in the same interval, apply the concurrent constraint attribution model (Section K); never double-count time or value.

Attribution rule: Attribution recorded as PRIMARY / CONTRIBUTORY / CONCURRENT / SHARED_CAUSATION / UNATTRIBUTED per governed rule; false precision prohibited.

Evidence ref:

M-12 · AuthorizationQueueTimeDEFINEDhours

Operational definition: Time a package waits on an authority holder, separated from time waiting on a technical condition.

Measurement window: QueuedForAuthority → AuthorityDecision

Source: Work control transaction log

Collection method: Event extract with wait-reason classification

Owner: NOT_YET_CONFIRMED — measurement owner nomination pending

Frequency: Per submission

Timestamp basis: Transaction log

Exclusions: Waits caused by planned shift boundaries where no authority holder is rostered — recorded separately.

Correction rule: Corrections permitted only with recorded reason, corrector identity and timestamp; original value retained and never overwritten.

Missing data rule: Missing values are recorded as MISSING with reason; they are never imputed, averaged or back-filled.

Concurrent constraint rule: Where more than one constraint is active in the same interval, apply the concurrent constraint attribution model (Section K); never double-count time or value.

Attribution rule: Attribution recorded as PRIMARY / CONTRIBUTORY / CONCURRENT / SHARED_CAUSATION / UNATTRIBUTED per governed rule; false precision prohibited.

Evidence ref:

J · Measurement event model

Measurement is event-based, using actual process events. TimeSaved, TimeReleased and ProductiveTimeCaptured remain separate concepts and are never collapsed into a single productivity metric.

ScheduledNOT_YET_CONFIRMED

Definition: Work placed into a schedule with a planned window.

PreparedNOT_YET_CONFIRMED

Definition: Supervisor declares preparation complete.

SubmittedNOT_YET_CONFIRMED

Definition: Package submitted for review or authorization.

ReviewedNOT_YET_CONFIRMED

Definition: Technical review performed.

ReturnedNOT_YET_CONFIRMED

Definition: Package returned for correction.

ApprovedNOT_YET_CONFIRMED

Definition: Authority decision recorded.

ReleasedNOT_YET_CONFIRMED

Definition: Work released to the field.

WorkStartedNOT_YET_CONFIRMED

Definition: Physical work commences at the workface.

HeldNOT_YET_CONFIRMED

Definition: Work suspended for a recorded cause.

ResumedNOT_YET_CONFIRMED

Definition: Work resumes after a hold.

CompletedNOT_YET_CONFIRMED

Definition: Work completed and recorded.

TimeSaved

Meaning: Reduction in elapsed time to reach the same process event, attributable to a specific cause.

TimeReleased

Meaning: Time no longer consumed by a person on a task, which may or may not be redeployed.

ProductiveTimeCaptured

Meaning: Time actually converted into productive workface activity, evidenced at the workface.

Collapsing these three into one productivity figure produces unsupportable value claims and is prohibited.

K · Concurrent constraint attribution model

The causal attribution rule is frozen before BEFORE collection begins. Where multiple constraints exist simultaneously, delay or value is never double-counted. Where attribution cannot be reliably established, use UNATTRIBUTED or SHARED_CAUSATION per governed rule.

Register fields: Constraint_ID · PrimaryCause · ContributoryCause · ConcurrentCause · AttributionBasis · Owner · Evidence

PRIMARY

Use: One constraint demonstrably determined the outcome and would have done so alone.

CONTRIBUTORY

Use: A constraint materially extended the outcome but was not sufficient alone.

CONCURRENT

Use: Two or more constraints were independently sufficient over the same interval; time is counted once.

SHARED_CAUSATION

Use: Causation is genuinely joint and cannot be separated with the available evidence; the interval is recorded once and flagged.

UNATTRIBUTED

Use: No defensible causal basis exists; the interval is retained but excluded from any attributed value claim.

CA-EX-01

Scenario: Material unavailable and area not released over the same 4-hour interval.

Treatment: CONCURRENT — 4 hours counted once; both causes recorded; no 8-hour total.

CA-EX-02

Scenario: Authorization waiting on an authority holder while a document version query is also open.

Treatment: PRIMARY = authority wait if work could not proceed regardless; document query recorded as CONTRIBUTORY.

CA-EX-03

Scenario: Start delay with no recorded cause.

Treatment: UNATTRIBUTED — retained in elapsed data, excluded from attributed value.

ATTRIBUTION_RULE_DEFINED (DesignEvidence). Not yet ratified by a competent measurement authority — owner nomination pending.

L · Baseline period governance

No duration is invented. Baseline sufficiency is determined by evidence quality and operational representativeness, decided by competent authority — not by an arbitrary day count.

StartDateNOT_STARTED
CoverageNOT_YET_AVAILABLE
WorkTypesCoveredNOT_YET_AVAILABLE — must span the disciplines actually present in the CV-07 container
ShiftsCoveredNOT_YET_AVAILABLE — must include the shift patterns actually worked
LocationsCoveredNOT_YET_AVAILABLE — CV-07 container; canonical reference DEPENDENCY_HELD
ConstraintTypesObservedNOT_YET_AVAILABLE — representativeness requires observation of the constraint types that actually recur
DataCompletenessNOT_YET_AVAILABLE
OperationalRepresentativenessNOT_YET_AVAILABLE
CompetentReviewerNOT_YET_NOMINATED
BaselineSufficiencyDecisionNOT_YET_MADE — cannot precede collection

M · BC-09 anti-contamination register

Default is NO wherever material workflow contamination is plausible. The baseline is never contaminated in order to accelerate Pilot execution. If contamination occurs, it is not repaired by reconstruction: a BC09_CONTAMINATION_EVENT is raised and escalated for a competent-authority decision on whether a new baseline window is required.

NONE RECORDEDBC09Protection = ACTIVE. PilotExposure = PROHIBITED.

Basis: No Pilot capability has been exposed to any field user; no workflow, form, prompt, alert or support structure has changed.

AC-01 · Pilot UI exposure to field usersNOT ALLOWED BEFORE BASELINE

Potential baseline impact: Directly changes the preparation and decision method being measured; irreversible contamination of BEFORE.

Decision authority: Pilot Sponsor + Measurement Owner (both unassigned)

Restriction: PROHIBITED until prospective BEFORE collection has formally commenced and the baseline window is declared closed by competent authority.

Evidence: No exposure has occurred.

AC-02 · Field demonstrations of the Pilot capability to execution personnelNOT ALLOWED BEFORE BASELINE

Potential baseline impact: Anticipation effects and behavioural change in the measured population.

Decision authority: Pilot Sponsor

Restriction: PROHIBITED for personnel inside the measured population; permitted only for non-measured governance audiences with attendance recorded.

Evidence: None conducted.

AC-03 · User training that changes the execution method being measuredNOT ALLOWED BEFORE BASELINE

Potential baseline impact: Alters the very process under baseline observation.

Decision authority: Pilot Sponsor + ES&H

Restriction: Material-preparation permitted; delivery to the measured population PROHIBITED before baseline start.

Evidence: Not delivered.

AC-04 · Readiness alerts / notifications to field usersNOT ALLOWED BEFORE BASELINE

Potential baseline impact: Introduces new detection lead time, corrupting M-03 and M-09.

Decision authority: Measurement Owner

Restriction: PROHIBITED.

Evidence: Not enabled.

AC-05 · New SIMOPS coordination routineNOT ALLOWED BEFORE BASELINE

Potential baseline impact: Changes late-detection rate and coordination effort under measurement.

Decision authority: ES&H Lead + Measurement Owner

Restriction: PROHIBITED where it changes the current coordination method; passive recording of the existing routine is permitted.

Evidence: Not introduced.

AC-06 · Automated prepopulation of forms or packagesNOT ALLOWED BEFORE BASELINE

Potential baseline impact: Directly reduces measured preparation and duplicate-entry effort.

Decision authority: Measurement Owner

Restriction: PROHIBITED.

Evidence: Not enabled.

AC-07 · New dashboards visible to the measured populationNOT ALLOWED BEFORE BASELINE

Potential baseline impact: Changes information availability and decision timing.

Decision authority: Pilot Sponsor

Restriction: PROHIBITED for the measured population; governance-only dashboards permitted where field users have no access.

Evidence: None deployed to field.

AC-08 · New work-control prompts or decision supportNOT ALLOWED BEFORE BASELINE

Potential baseline impact: Changes the decision sequence being measured.

Decision authority: Work Control Lead + Measurement Owner

Restriction: PROHIBITED.

Evidence: Not enabled.

AC-09 · New digital forms replacing current formsNOT ALLOWED BEFORE BASELINE

Potential baseline impact: Replaces the artefact whose handling time is being measured.

Decision authority: Work Control Lead

Restriction: PROHIBITED.

Evidence: Not introduced.

AC-10 · Digital IPERC support in the fieldNOT ALLOWED BEFORE BASELINE

Potential baseline impact: Alters hazard identification behaviour and timing.

Decision authority: ES&H Lead

Restriction: PROHIBITED.

Evidence: Not introduced.

AC-11 · Forecast logic exposed to plannersNOT ALLOWED BEFORE BASELINE

Potential baseline impact: Changes planning behaviour and constraint detection lead time.

Decision authority: Measurement Owner

Restriction: PROHIBITED.

Evidence: Not enabled.

AC-12 · New support structure (L1/L2) available to field usersNOT ALLOWED BEFORE BASELINE

Potential baseline impact: Changes clarification volume and resolution time (M-08, M-04).

Decision authority: Support Owner (unassigned — Mesa 2 BC-07)

Restriction: PROHIBITED before baseline start; existing support arrangements remain unchanged.

Evidence: No new support deployed.

AC-13 · Passive observation of existing work (observer present, non-advising)ALLOWED BEFORE BASELINE

Potential baseline impact: Low, but a Hawthorne effect is possible; mitigated by observation protocol and by observing across the full baseline window.

Decision authority: Measurement Owner

Restriction: ALLOWED as NON_INTRUSIVE_PREPARATION. Observer must not advise, prompt, correct or expedite. Effect noted as a known limitation.

Evidence: Protocol defined (DesignEvidence).

AC-14 · Retrospective reconstruction of BEFORE from historical records or averagesNOT ALLOWED BEFORE BASELINE

Potential baseline impact: Produces an unattributable baseline and invalidates causal claims.

Decision authority: Competent measurement authority

Restriction: PROHIBITED as a baseline. Permitted only as formally approved supplementary reference, explicitly labelled as non-baseline.

Evidence: Not used.

N · Allowed / prohibited pre-baseline activities

NON_INTRUSIVE_PREPARATION

  • Evidence gathering from systems and owners, with no change to field behaviour.
  • Owner confirmation and nomination of measurement accountabilities.
  • System participation confirmation (read-only feasibility, no field-facing change).
  • Measurement instrumentation setup that does not alter the observed process.
  • Passive observation under a non-advising protocol.
  • Timestamp validation and clock-source verification.
  • Source mapping and field/attribute traceability.
  • Training material preparation — prepared, not delivered to the measured population.

PILOT_INTERVENTION — PROHIBITED

  • Changing field workflow or sequencing.
  • Prompting readiness decisions.
  • Exposing new digital interfaces to users.
  • Altering approvals or authority routing.
  • Automated recommendations that affect decisions.
  • Introducing new support, alerts, dashboards or forms into the measured population.

Any activity whose plausible effect is a change in the measured method is classified as PILOT_INTERVENTION and is prohibited before baseline start, regardless of intent.

Prospective BEFORE collection readiness test

MetricDefinitionCompleteMET (DesignEvidence)

Note: All 12 metrics have operational definitions, units, start/end events, exclusions and data-quality rules.

SourceAvailableNOT MET

Note: No measurement source has confirmed participation; work-control and schedule participation unresolved (BC-01).

OwnerConfirmedNOT MET

Note: No measurement owner nominated for any metric (Mesa 2 dependency).

TimestampReliableNOT MET

Note: Clock source, timezone handling and event fidelity not validated against any real extract.

MissingDataRuleDefinedMET (DesignEvidence)

Note: MISSING recorded with reason; imputation prohibited.

CorrectionRuleDefinedMET (DesignEvidence)

Note: Corrections attributable, original retained.

AttributionRuleDefinedMET (DesignEvidence)

Note: Concurrent attribution model defined; ratification by competent authority pending.

NoPilotExposureConfirmedMET

Note: No Pilot exposure has occurred; anti-contamination register default is NO.

FieldScopeStableEnoughNOT MET

Note: CV-07 field scope has unresolved WorkPackage, JobCard, crew, window and canonical Location attributes.

Privacy/RetentionDependencyKnownNOT MET

Note: BC-05 data minimisation and retention determination outstanding (Mesa 1), affecting competency, fitness and observation data.

5 of 10 conditions met, all at DesignEvidence level. Conditions are non-compensable: BC-09 = REMAINS_OPEN and prospective collection may not commence.

O · Positive & negative field traces

RealWorkDemandRealLocationFieldPrerequisitesFieldOwnerMeasurementScopeProspectiveCaptureReady
RealWorkDemandNOT_DEMONSTRATED

Basis: No authoritative work-control extract received.

RealLocationDEPENDENCY_HELD

Basis: Physical context describable; canonical identity unresolved (Mesa 1 / ADR-14).

FieldPrerequisitesNOT_DEMONSTRATED

Basis: 17 prerequisite domains defined; 0 carry operational evidence.

FieldOwnerNOT_DEMONSTRATED

Basis: No accountable field owner nominated (Mesa 2 dependency).

MeasurementScopeDEFINED

Basis: 12 frozen metrics with operational definitions and data-quality rules (DesignEvidence).

ProspectiveCaptureReadyNOT_REACHED

Basis: 5 of 10 collection readiness conditions unmet; collection may not commence.

This trace demonstrates field and measurement readiness structure only. It does not execute the Pilot readiness decision and confers no Phase 6B authorization.

Negative traces

NT-01NOT_READY / HOLDsideEffect = NONE

Input: MissingMandatoryPrerequisite (any non-compensable domain unresolved)

Note: No partial authorization, no downgrade to CONDITIONAL, no state written to any source system.

NT-02PROHIBITEDsideEffect = NONE

Input: PilotExposureBeforeBaseline (attempted exposure of Pilot capability to a measured field user)

Note: BC09Protection = ACTIVE. The request is refused and recorded in the anti-contamination register; no exposure occurs.

NT-03REFUSEDsideEffect = NONE

Input: Request to reconstruct BEFORE from historical averages to accelerate Pilot

Note: Reconstruction is admissible only as formally approved supplementary reference, never as baseline.

NT-04REFUSED — OUT_OF_AUTHORITYsideEffect = NONE

Input: Request to elect BC-06 Path A or Path B from Mesa 3

Note: BC-06 election remains Mesa 1 authority.

Field readiness negative scenarios

NS-01 · Location unavailableDOCUMENTED (DesignEvidence) — not field-exercised.

Expected behaviour: Readiness resolves NOT_READY / HOLD for every JobCard in the container; no substitution of an alternative Location; sideEffect = NONE.

NS-02 · Work package cancelledDOCUMENTED — not field-exercised.

Expected behaviour: All dependent readiness context is invalidated, not carried forward; measurement records the cancellation event rather than deleting the case.

NS-03 · Crew changedDOCUMENTED — not field-exercised.

Expected behaviour: Competency and fitness re-evaluation is mandatory; prior confirmations do not transfer to new personnel.

NS-04 · Equipment unavailableDOCUMENTED — not field-exercised.

Expected behaviour: Non-compensable prerequisite unresolved → READY NOT PERMITTED; no averaging against satisfied domains.

NS-05 · Material unavailableDOCUMENTED — not field-exercised.

Expected behaviour: HOLD with named blocker and owner; no silent substitution of an equivalent material without engineering authority.

NS-06 · Environmental restriction (e.g. wind limit breach)DOCUMENTED — not field-exercised.

Expected behaviour: Immediate STOP/HOLD on affected activities at the Location; restriction applies to the container, not only the triggering activity.

NS-07 · Client / owner release absentDOCUMENTED — not field-exercised.

Expected behaviour: HOLD; owner release cannot be assumed from prior releases or from schedule presence.

NS-08 · Concurrent work introduced after authorizationDOCUMENTED — not field-exercised.

Expected behaviour: Location-level re-evaluation triggered (CUM rules); a previously valid pairwise PASS does not survive a changed concurrent set.

NS-09 · Critical control dependency unresolvedDOCUMENTED — not field-exercised.

Expected behaviour: Activity requiring critical control cannot be READY; dependency recorded as HELD_BY_MESA_1; no simulated verification.

NS-10 · Measurement source unavailableDOCUMENTED — not field-exercised.

Expected behaviour: Affected metric is recorded as source-unavailable with reason; no proxy substitution, no historical back-fill, no fabricated value.

P · Mesa 1 / Mesa 2 ↔ Mesa 3 dependency register

External dependencies are never counted as Mesa 3 failures and never hidden inside a generic HOLD. Mesa 3 may progress its own evidence acquisition in parallel while these remain open.

FP-01 Canonical Location identity / D. Location validationMESA_1BC-01 interface participationCLOSURE_DEPENDENCY

Can progress independently: YES

Can close field condition: NO

Can execute Pilot: NO

Evidence required: Authorized participation of the Location source and a steward-issued canonical reference for CV-07.

FP-02 / E. Work demand validationMESA_1BC-01 interface participationCLOSURE_DEPENDENCY

Can progress independently: YES

Can close field condition: NO

Can execute Pilot: NO

Evidence required: Authorized work-control extract for the Pilot window.

H. Field user identity and attributable participationMESA_1BC-02 real IAMEXECUTION_DEPENDENCY

Can progress independently: YES

Can close field condition: NO

Can execute Pilot: NO

Evidence required: Real identity resolution for named field participants with role assertions.

E. LifecycleAuthorityResolved / FP-15 restrictionsMESA_1BC-03 lifecycle authority (ADR-15 / ADR-17)CLOSURE_DEPENDENCY

Can progress independently: YES

Can close field condition: NO

Can execute Pilot: NO

Evidence required: Ratified CV-07 transition sets and named lifecycle authority.

FP-08 / FP-09 competency and fitness data handling; observation dataMESA_1BC-05 data minimisation and retentionCLOSURE_DEPENDENCY

Can progress independently: YES

Can close field condition: NO

Can execute Pilot: NO

Evidence required: Approved minimisation, retention and privacy determination covering measurement and observation data.

FP-17 / G. Critical Control field participationMESA_1BC-06 Critical Control Path A/BCLOSURE_DEPENDENCY

Can progress independently: NO

Can close field condition: NO

Can execute Pilot: NO

Evidence required: Recorded competent-authority election of Path A (real critical control) or Path B (formal rescope) with residual risk.

B / H. Field owner, supervisor and steward nominationMESA_2BC-04 stewardship and governance assignmentCLOSURE_DEPENDENCY

Can progress independently: YES

Can close field condition: NO

Can execute Pilot: NO

Evidence required: Named, documented accountabilities including Location steward and measurement owner.

M / N. Support arrangements during baseline and PilotMESA_2BC-07 operational supportEXECUTION_DEPENDENCY

Can progress independently: YES

Can close field condition: YES

Can execute Pilot: NO

Evidence required: Support model staffed and demonstrably independent of the design team — noting new support must not be introduced into the measured population before baseline start.

Q · BC-08 / BC-09 closure register

BC-08 — Field Prerequisites / Execution ReadinessREMAINS_OPENEvidenceQuality NONE0/10

DesignEvidence: Field readiness model across 17 non-aggregated domains, prerequisite register, negative scenarios and failure behaviour defined.

OperationalClosureEvidence: None. No field-verified workfront, owner, window, crew or prerequisite confirmation received.

Note: CLOSED_WITH_CONTROL remains available only where competent authority explicitly accepts a named external dependency; no such acceptance exists today.

BC-09 — Prospective BEFORE Measurement ReadinessREMAINS_OPENEvidenceQuality NONE4/10

DesignEvidence: 12 frozen metrics operationally defined, event model, attribution model, baseline governance and anti-contamination register.

OperationalClosureEvidence: None. Collection has not commenced; sources, owners and timestamp basis unconfirmed.

Note: Collection is not even READY_TO_COLLECT: 5 of 10 readiness-test conditions are unmet. BC-09 is never closed on design readiness alone.

BC-08 closure criteria

CV-07 workfront exists (field-verified)PENDING EVIDENCE

Basis: No field walk-down or work-control extract received.

Location is identifiable and usablePENDING EVIDENCE

Basis: DEPENDENCY_HELD — canonical Location identity unresolved (Mesa 1 / ADR-14).

Work demand is realPENDING EVIDENCE

Basis: WorkDemandExists NOT_DEMONSTRATED; fabrication prohibited.

Required disciplines / crew are knownPENDING EVIDENCE

Basis: Rosters and discipline mix not supplied.

Enabling conditions sufficiently availablePENDING EVIDENCE

Basis: 0 of 17 prerequisite domains carry operational evidence.

Field owners identifiedPENDING EVIDENCE

Basis: No accountable field owner or supervisor nominated.

Planned execution window existsPENDING EVIDENCE

Basis: No window issued; Pilot execution on HOLD.

SIMOPS context is knownPENDING EVIDENCE

Basis: LocationConcurrentWorkSet NOT_ESTABLISHED.

Field prerequisites can be verifiedPENDING EVIDENCE

Basis: Verification method defined; no verifier assigned and no verification performed.

No material unknown prevents Pilot field executionPENDING EVIDENCE

Basis: Multiple material unknowns remain across scope, identity, authority and critical control.

BC-09 closure criteria

All 12 metrics operationally definedDEMONSTRATED

Basis: DesignEvidence — definitions, units, events, exclusions and data-quality rules complete.

Sources confirmedPENDING EVIDENCE

Basis: No source has confirmed participation.

Owners confirmedPENDING EVIDENCE

Basis: No measurement owner nominated.

Timestamp basis validPENDING EVIDENCE

Basis: Clock source and event fidelity unvalidated.

Data-quality rules existDEMONSTRATED

Basis: DesignEvidence — missing-data and correction rules defined.

Concurrent attribution logic existsDEMONSTRATED

Basis: DesignEvidence — attribution classes and non-double-count rule defined; ratification pending.

Prospective collection has formally startedPENDING EVIDENCE

Basis: NOT_STARTED — this alone prevents closure.

No Pilot contamination occurredDEMONSTRATED

Basis: No exposure; anti-contamination register default NO; no BC09_CONTAMINATION_EVENT.

Evidence exists that the baseline can be reconstructedPENDING EVIDENCE

Basis: No collected record exists to reconstruct.

Baseline sufficiency can eventually be assessed prospectivelyPENDING EVIDENCE

Basis: Competent reviewer not nominated; representativeness criteria cannot yet be evaluated.

R · Evidence acquisition & retest queue

M3-ER-01 · Construction ManagementFIELD_SCOPEBC-08

Request: Nominate the accountable Field Owner and Supervisor for the CV-07 Pilot workfront, with position and authority basis.

Acceptance criterion: Named position holder with documented accountability and effective date.

M3-ER-02 · Work ControlFIELD_SCOPEBC-08

Request: Provide the authoritative WorkPackage and JobCard extract for the candidate CV-07 window (no fabrication, no reformatting).

Acceptance criterion: System extract with identifiers, scope, discipline, planned dates and schedule reference.

M3-ER-03 · Location Steward / Enterprise ArchitectureFIELD_SCOPEBC-08

Request: Issue the canonical Location reference for the CV-07 container under ADR-14 Option C, with boundary definition.

Acceptance criterion: Steward-issued canonical reference with effective date and boundary description.

M3-ER-04 · Construction planningFIELD_SCOPEBC-08

Request: Confirm planned execution window, shift pattern, discipline mix and crew composition.

Acceptance criterion: Planned window and roster valid for the specific shifts.

M3-ER-05 · Area Construction SuperintendentFIELD_PREREQUISITESBC-08

Request: Provide area release, access conditions and physical walk-down confirmation for the workfront.

Acceptance criterion: Signed area release plus dated walk-down record.

M3-ER-06 · Engineering Document ControlFIELD_PREREQUISITESBC-08

Request: Confirm released engineering applicable to the workfront at pinned revisions.

Acceptance criterion: Document list with revision, status and effective date.

M3-ER-07 · Materials / WarehouseFIELD_PREREQUISITESBC-08

Request: Confirm material availability and reservation against the work package.

Acceptance criterion: Reservation or issue record referencing the package.

M3-ER-08 · Construction Equipment & ToolsFIELD_PREREQUISITESBC-08

Request: Confirm equipment allocation and certification validity, and tool inspection validity, for the window.

Acceptance criterion: Certification and inspection validity dates spanning the window.

M3-ER-09 · Training & Competency / Occupational HealthFIELD_PREREQUISITESBC-08

Request: Confirm the minimised competency and fitness status feed (status and validity only) for assigned personnel.

Acceptance criterion: Status-only feed compliant with the BC-05 minimisation determination.

M3-ER-10 · ES&H / SIMOPSFIELD_PREREQUISITESBC-08

Request: Provide the concurrent work set for the CV-07 Location container over the candidate window, including planned and active work.

Acceptance criterion: Complete concurrent set with time overlaps and interaction attributes; completeness attested by ES&H.

M3-ER-11 · Operations InterfaceFIELD_PREREQUISITESBC-08

Request: Provide active operational restrictions, exclusion zones and temporary modifications applicable to the container.

Acceptance criterion: Register extract current at the date of issue.

M3-ER-12 · Client InterfaceFIELD_PREREQUISITESBC-08

Request: Confirm whether owner release is required for the workfront and, if so, provide the release.

Acceptance criterion: Written determination plus release document where applicable.

M3-ER-13 · Emergency ResponseFIELD_PREREQUISITESBC-08

Request: Confirm emergency response, rescue and evacuation provisions valid for the workfront and shift.

Acceptance criterion: Plan reference applicable to the location and task set.

M3-ER-14 · Pilot Sponsor / GovernanceMEASUREMENT_INSTRUMENTATIONBC-09

Request: Nominate the Measurement Owner and the competent reviewer for baseline sufficiency.

Acceptance criterion: Named accountabilities with authority basis (Mesa 2 dependency, recorded not absorbed).

M3-ER-15 · Work Control / SystemsMEASUREMENT_INSTRUMENTATIONBC-09

Request: Confirm availability of the process events (Scheduled…Completed) and provide a sample extract for timestamp validation.

Acceptance criterion: Sample extract enabling clock-source, timezone and event-fidelity validation.

M3-ER-16 · Per-metric source ownersMEASUREMENT_INSTRUMENTATIONBC-09

Request: Confirm source and owner for each of the 12 frozen metrics.

Acceptance criterion: 12 signed source/owner confirmations; partial confirmation does not advance the set.

M3-ER-17 · Measurement authorityMEASUREMENT_INSTRUMENTATIONBC-09

Request: Ratify the concurrent constraint attribution rule before collection begins.

Acceptance criterion: Recorded ratification with authority and date.

M3-ER-18 · Data Governance (BC-05 interface)MEASUREMENT_INSTRUMENTATIONBC-09

Request: Confirm privacy and retention treatment for observation, competency and fitness data used in measurement.

Acceptance criterion: Approved determination covering the measurement data set.

M3-ER-19 · Pilot SponsorMEASUREMENT_INSTRUMENTATIONBC-09

Request: Formally declare the prospective BEFORE collection start, with the anti-contamination register accepted and in force.

Acceptance criterion: Dated declaration; collection start is the only route out of NOT_STARTED.

Targeted retest queueQUEUE EMPTY

Rule: Targeted retest is triggered only when a Mesa 3 condition reaches EvidenceQuality ≥ SUFFICIENT_FOR_RETEST. No condition has reached PARTIAL. No Phase 6A integrated rerun is authorized.

Escalation register

M3-ESC-01

Issue: No accountable field owner exists for the Pilot workfront, so no party can be asked to confirm field prerequisites.

Authority: Construction Management / Pilot Sponsor

Risk: Evidence acquisition cannot start on the BC-08 lane.

M3-ESC-02

Issue: Measurement owner unnamed while BC-09 is time-irreversible — every day without prospective capture is a day of baseline that cannot be recovered.

Authority: Pilot Sponsor

Risk: Schedule pressure may later be used to justify contaminating or reconstructing the baseline.

M3-ESC-03

Issue: Pressure to demonstrate the Pilot to field users before baseline start.

Authority: Pilot Sponsor + Measurement Owner

Risk: Would trigger a BC09_CONTAMINATION_EVENT and require a new baseline window.

M3-ESC-04

Issue: BC-06 Path A/B unelected, leaving critical-control field participation undefined for a corridor with plausible critical risks.

Authority: Mesa 1 — Critical Risk Owner

Risk: No Pilot field execution can be authorized for critical-risk activities.

S · Mesa 3 final disposition

Disposition

FIELD_EXECUTION_AND_MEASUREMENT_HOLD

Field & Measurement Design Condition

FIELD_AND_MEASUREMENT_DESIGN_STRUCTURALLY_SOUND

BC-08

REMAINS_OPEN — Evidence acquisition required · 0/10 demonstrated

BC-09

REMAINS_OPEN — Prospective BEFORE collection has not formally commenced · 4/10 demonstrated (DesignEvidence) · 6/10 pending OperationalClosureEvidence

Operational Closure Evidence

NOT_YET_SUFFICIENT

Collection Readiness

5/10 conditions met (DesignEvidence) — collection may not commence

Prospective Baseline

NOT_STARTED — not READY_TO_COLLECT

Pilot Exposure

PROHIBITED — BC09Protection = ACTIVE

Contamination

NO BC09_CONTAMINATION_EVENT

Confirmed Failed

0 criteria confirmed failed — based on current evidence set

Structural Contradiction

NONE IDENTIFIED

Retest Eligibility

NOT YET ELIGIBLE

External Dependencies

6 Mesa 1 dependencies (BC-01, BC-02, BC-03, BC-05, BC-06) and 2 Mesa 2 dependencies (BC-04, BC-07) recorded as external, not as Mesa 3 failures.

Mesa 3 cannot yet prove that the CV-07 field is real and executable, nor that measurement can begin prospectively without changing what is being measured. The field readiness model and the prospective BEFORE measurement design are structurally sound and fail closed, but they are evidentially empty: no field-verified workfront, no nominated field owner, no confirmed measurement source or owner, and no commenced collection. Mesa 3 therefore returns FIELD_EXECUTION_AND_MEASUREMENT_HOLD, with BC-08 and BC-09 REMAINS_OPEN, Pilot exposure PROHIBITED, and the Mesa 1 / Mesa 2 dependencies recorded separately and visibly. Readiness to measure is not authorization to Pilot; neither is available today.

Authorized next activity

  • Acquire BC-08 field scope and prerequisite evidence from the nominated competent owners (M3-ER-01…13).
  • Acquire BC-09 measurement instrumentation evidence and nominate the measurement owner (M3-ER-14…18).
  • On satisfaction of the collection readiness test, obtain the formal prospective BEFORE collection start declaration (M3-ER-19).
  • No Phase 6A integrated rerun, no Phase 6B execution, no Pilot exposure.