Phase 6A — Pre-Execution Readiness Closure (Rev.3)

Phase 6A has been executed as a readiness determination against the frozen Pilot Definition Baseline. No prerequisite has been converted into an evidence-backed operational state: every enterprise interface remains NOT_YET_VALIDATED, enterprise identity remains unresolved, the Pilot-scope lifecycle authority decisions (ADR-15 / ADR-17) remain open, mandatory stewardship roles remain unstaffed, CA-04 classification remains unresolved, field prerequisites are unconfirmed, and BEFORE measurement has not started prospectively. Critical Control participation remains SIMULATED and has not been rescoped by competent authority. Under the Phase 6A GO criteria, all ten gates fail; the disposition is therefore HOLD.

HOLD — CONTROLLED PILOT EXECUTION NOT AUTHORIZEDGO criteria met 1/10Blocking conditions 10

The Phase 6 Pilot Definition Baseline is reproduced unchanged. No journey, metric, protocol or scope element has been altered, softened or removed. No change was made to improve the likelihood of a Pilot PASS.

A · Executive summary — prohibited claims at this stage

  • Executing any of the twenty Pilot journeys
  • Claiming BEFORE/AFTER results, savings or adoption outcomes
  • Treating a simulated Critical Control journey as production-level integration evidence
  • Reconstructing a BEFORE baseline retrospectively
  • Executing Phase 6B

Evidence GC-01…GC-05 and the field/measurement prerequisites, then re-run Phase 6A. Phase 6B begins only after a formal GO — CONTROLLED PILOT EXECUTION AUTHORIZED.

§2 · Frozen Pilot Definition Baseline — integrity check

CV-07 corridorFour LocationsThree disciplines (mechanical / electrical / instrumentation)Concurrent Job CardsTwelve BEFORE metrics and their measurement methodSource participation registerTwenty Pilot journeys (J-01…J-20)SIMOPS protocolLocation Continuity protocolForecast Readiness protocolOffline / Reconciliation protocolSix-class workaround root-cause modelDesign-team-withdrawn stewardship testValue-chain modelCausal attribution methodArchitecture Drift RegisterPilot Acceptance Register

Any requested change to the frozen Pilot Definition must be classified and logged before it is applied. Changes must never be made to improve the likelihood of a Pilot PASS. Logged change requests: 0.

C · Enterprise Interface Validation Register (GC-01)

Engica Q4 / TSI
NOT_CONNECTEDNOT_READY

PilotObject: Safety Document, Permit, Isolation, Work Pack state

AuthorityClass: SOURCE_MASTER (authorization control)

Mechanism: UNKNOWN — no interface catalogue supplied; API existence not evidenced.

Read / Write / Event: NOT_DEMONSTRATED · PROHIBITED for pilot (no write-back authorized) · NOT_DEMONSTRATED

VersionBehaviour: UNDEFINED — decision pinning cannot be evidenced.

FailureBehaviour: Fail-closed by design: unmapped/unavailable state ⇒ HOLD.

EvidenceOfValidation: NONE — no validation artefact produced by the source system owner.

SupportOwner: UNASSIGNED

Aconex
NOT_CONNECTEDNOT_READY

PilotObject: Controlled document, revision, transmittal

AuthorityClass: SOURCE_MASTER (document control)

Mechanism: UNKNOWN — manual copy is not an interface.

Read / Write / Event: NOT_DEMONSTRATED · PROHIBITED · NOT_DEMONSTRATED

VersionBehaviour: Revision pinning designed, not demonstrated.

FailureBehaviour: Unpinnable revision ⇒ condition invalid ⇒ HOLD.

EvidenceOfValidation: NONE — no validation artefact produced by the source system owner.

SupportOwner: UNASSIGNED

Primavera P6
NOT_CONNECTEDNOT_READY

PilotObject: Activity, lookahead window, planned execution date

AuthorityClass: SOURCE_MASTER (schedule)

Mechanism: UNKNOWN — periodic export assumed, not evidenced.

Read / Write / Event: NOT_DEMONSTRATED · PROHIBITED · NOT_DEMONSTRATED

VersionBehaviour: Snapshot identity required for Forecast Readiness; undemonstrated.

FailureBehaviour: Stale schedule ⇒ forecast marked INVALID, never optimistic.

EvidenceOfValidation: NONE — no validation artefact produced by the source system owner.

SupportOwner: UNASSIGNED

Critical Control source (Life-Critical)
SIMULATEDNOT_READY

PilotObject: Life-Critical verification / critical control confirmation

AuthorityClass: SOURCE_MASTER (non-compensable control)

Mechanism: None — prototype simulation only.

Read / Write / Event: SIMULATED · PROHIBITED · NONE

VersionBehaviour: N/A

FailureBehaviour: Absent real control evidence ⇒ non-compensable failure ⇒ STOP.

EvidenceOfValidation: NONE — no validation artefact produced by the source system owner.

SupportOwner: UNASSIGNED

Competency / training register
NOT_CONNECTEDNOT_READY

PilotObject: Competency validity, expiry

AuthorityClass: SOURCE_MASTER (competency)

Mechanism: UNKNOWN

Read / Write / Event: NOT_DEMONSTRATED · PROHIBITED · NOT_DEMONSTRATED

VersionBehaviour: Expiry timestamps required for forecast; unevidenced.

FailureBehaviour: Unknown validity ⇒ treated as invalid (fail-closed).

EvidenceOfValidation: NONE — no validation artefact produced by the source system owner.

SupportOwner: UNASSIGNED

Enterprise IAM / directory
NOT_CONNECTEDNOT_READY

PilotObject: Identity, role, delegation, authority expiry

AuthorityClass: SOURCE_MASTER (identity)

Mechanism: UNKNOWN — federation protocol not confirmed.

Read / Write / Event: NOT_DEMONSTRATED · PROHIBITED · NOT_DEMONSTRATED

VersionBehaviour: N/A

FailureBehaviour: Unresolved identity ⇒ no authorization action offered.

EvidenceOfValidation: NONE — no validation artefact produced by the source system owner.

SupportOwner: UNASSIGNED

  • An interface is not integrated because its data can be manually copied.
  • No API is assumed to exist; capability must be demonstrated by the source system owner.
  • Any interface required by a mandatory Pilot decision must hold a validated participation mode before GO.

F · Critical Control participation decision

Current classification: SIMULATED

Path A: A real governed Critical Control source participates with evidence-backed authority and interface behaviour.

Path B: Competent governance formally rescopes the Life-Critical journey and classifies it SIMULATED_ONLY / NON_ACCEPTANCE_EVIDENCE.

Decision taken: NONE — neither Path A nor Path B has been exercised by competent authority.

Consequence: The Life-Critical Pilot journey is NOT EXECUTABLE as Pilot evidence. It must not be silently weakened, and a simulated journey cannot support any claim of production-level Critical Control integration.

NOT_READY

D · IAM / Authority readiness (GC-02)

ResolvedIdentityNOT_READY

Requirement: Authenticated enterprise identity resolvable to one accountable person per Pilot actor.

Evidence: None — prototype uses a declared session identity.

RoleResolutionNOT_READY

Requirement: Roles resolved server-side from an authoritative source.

Evidence: None — roles are client-selected in the prototype.

ProjectScopeNOT_READY

Requirement: Authority bounded to the Pilot project.

Evidence: Designed only.

AreaScopeNOT_READY

Requirement: Authority bounded to AREA-3100 / CV-07.

Evidence: Designed only.

ActivityScopeNOT_READY

Requirement: Authority bounded to discipline and activity class.

Evidence: Designed only.

RiskScopeNOT_READY

Requirement: Authority bounded by risk class; Life-Critical requires elevated authority.

Evidence: Designed only.

DelegationNOT_READY

Requirement: Delegation issued, bounded, recorded, revocable.

Evidence: Prototype model exists; no enterprise-backed delegation.

AuthorityExpiryNOT_READY

Requirement: Expiry enforced at decision time; expired authority denies.

Evidence: Enforced in prototype only.

DeniedActionNOT_READY

Requirement: Denials produce attributable evidence; UI hiding is not enforcement.

Evidence: Prototype records denials; no enterprise enforcement point.

EvidenceRefNOT_READY

Requirement: Reconstructable who / what / when / on-what-basis.

Evidence: Prototype evidence chain only.

CanViewCanProposeCanConfirmCanValidateCanApproveCanAuthorizeCanAdminister

UI hiding is not accepted as authority enforcement. No Pilot journey involving real authorization may execute with unresolved identity.

GC-03 · Pilot authority & lifecycle (ADR-15 / ADR-17)

Job Card (CV-07 scope)NOT_READY

LifecycleOwner: UNRESOLVED — ADR-15 open

StateOwner: UNRESOLVED

TransitionAuthority: UNRESOLVED — candidate: discipline supervisor within Location scope

ValidTransition: PLANNED → READY_FOR_EXECUTION only when all mandatory conditions are VALID and applicable.

InvalidTransition: Any transition to READY with an open non-compensable failure; any auto-advance on timeout.

EvidenceRequired: Pinned source versions, applicability decision, human confirmation with attribution.

DelegationRule: Bounded, time-limited, recorded; never implicit.

AuthorityUnavailable: Fail-closed: remain at current state, surface HOLD; never auto-advance.

Temporary ModificationNOT_READY

LifecycleOwner: UNRESOLVED — ADR-17 open

StateOwner: UNRESOLVED

TransitionAuthority: UNRESOLVED

ValidTransition: Only with an in-date authorization and an owning discipline authority.

InvalidTransition: Continuation past expiry; inheritance across Location handover.

EvidenceRequired: Authorization record, expiry, removal plan.

DelegationRule: Not delegable below the authorizing discipline authority.

AuthorityUnavailable: STOP for dependent work.

Location readiness contextNOT_READY

LifecycleOwner: ADR-14 Location Steward (role defined, unstaffed)

StateOwner: Location Steward

TransitionAuthority: Location Steward with ES&H concurrence for SIMOPS-affecting change

ValidTransition: Context persists across discipline handover; authorization never inherits.

InvalidTransition: Reusing a prior discipline's authorization for a new discipline.

EvidenceRequired: Re-evaluated applicability set with USED / REVALIDATED / RENEWED / REJECTED per condition.

DelegationRule: Backup steward only, named in advance.

AuthorityUnavailable: DISABLED_SAFE for the Location.

Only lifecycle/authority decisions required by CV-07 are in scope. Broader ADR questions remain deliberately open rather than being closed by convenience. HOLD, STOP and fail-closed behaviour are preserved unchanged.

E · Stewardship Assignment Register (GC-04)

Location Stewardship (per Pilot Location ×4)NOT_READY

NamedAssignment: UNASSIGNED — no named person nominated by resourcing authority.

Authority: Owns Location context, concurrency set, SIMOPS declaration.

Availability: Required across all Pilot shifts — not confirmed.

Backup: None named.

Escalation: Undefined.

Federation Mapping StewardshipNOT_READY

NamedAssignment: UNASSIGNED — no named person nominated by resourcing authority.

Authority: Owns source-to-canonical mapping and unmapped-state exceptions.

Availability: Not confirmed.

Backup: None named.

Escalation: Undefined.

Rule Governance (ADR-16)NOT_READY

NamedAssignment: UNASSIGNED — no named person nominated by resourcing authority.

Authority: Owns classification of non-compensable controls; no technical default may substitute.

Availability: Not confirmed.

Backup: None named.

Escalation: Undefined.

Product OwnershipNOT_READY

NamedAssignment: UNASSIGNED — no named person nominated by resourcing authority.

Authority: Owns Pilot scope and change classification.

Availability: Not confirmed.

Backup: None named.

Escalation: Undefined.

Integration SupportNOT_READY

NamedAssignment: UNASSIGNED — no named person nominated by resourcing authority.

Authority: Owns interface failure response within the Pilot window.

Availability: Not confirmed.

Backup: None named.

Escalation: Undefined.

Operational SupportNOT_READY

NamedAssignment: UNASSIGNED — no named person nominated by resourcing authority.

Authority: First-line field support for Pilot users.

Availability: Not confirmed.

Backup: None named.

Escalation: Undefined.

Change / Adoption (P3-TRN-01)NOT_READY

NamedAssignment: UNASSIGNED — no named person nominated by resourcing authority.

Authority: Owns funded training and adoption workstream.

Availability: Unfunded.

Backup: None named.

Escalation: Undefined.

  • A role may be organizationally assigned to a person for Pilot execution, but the architecture remains role-based.
  • Vacancy in a mandatory role ⇒ DISABLED_SAFE for the dependent capability; the Location issues no readiness decision.

§8 · Design-team-withdrawn test readiness

NormalSupportPath: Field user → Operational Support → Location Steward (context) or Federation Mapping Steward (source/mapping) → Rule Governance for classification questions.

EscalationPath: Unresolved within the shift → Product Ownership → Project governance. Safety-affecting ambiguity escalates immediately to ES&H authority and the work remains on HOLD.

EmergencyExceptionRule: Design-team involvement is permitted only for a defect that prevents fail-closed behaviour, must be logged as a stewardship-sustainability observation, and never counts as normal support.

Design team excluded activities

  • Resolving Location mapping exceptions
  • Deciding applicability or compensability questions
  • Interpreting readiness verdicts for field users
  • Repairing source-state exceptions
  • Answering evidence-reconstruction requests
  • Direct field user support
NOT_READYThe test cannot be run credibly while every stewardship role is unstaffed: with no organizational role to withdraw from, the result would be predetermined.

GC-05 · Governed classification / retention (CA-04)

CA-04 — Life-Critical control evidenceCLASSIFICATION_UNRESOLVED

Compensability: Fails closed as NON_COMPENSABLE pending governance decision.

Retention: UNRESOLVED — statutory horizon not confirmed for the Pilot jurisdiction.

AuthorityBasis: ADR-16 rule governance + legal/records

ApprovedBy: NONE · EffectiveFrom — · EvidenceRef NONE

CA-04 — Isolation / energy state evidenceCLASSIFICATION_UNRESOLVED

Compensability: Fails closed as NON_COMPENSABLE.

Retention: UNRESOLVED

AuthorityBasis: ES&H authority

ApprovedBy: NONE · EffectiveFrom — · EvidenceRef NONE

CA-04 — Competency validity evidenceCLASSIFICATION_UNRESOLVED

Compensability: Fails closed as NON_COMPENSABLE for Life-Critical activity.

Retention: UNRESOLVED

AuthorityBasis: Training governance

ApprovedBy: NONE · EffectiveFrom — · EvidenceRef NONE

CA-04 — Authorization / delegation recordsCLASSIFICATION_UNRESOLVED

Compensability: Not applicable (record class), but retention is mandatory for reconstruction.

Retention: UNRESOLVED

AuthorityBasis: Legal / records governance

ApprovedBy: NONE · EffectiveFrom — · EvidenceRef NONE

No technical default may decide compensability. Where a mandatory classification is unresolved, the system records CLASSIFICATION_UNRESOLVED and fails closed.

G · Field Prerequisite Register

Access to the four Pilot LocationsNOT_READY

Requirement: Permitted physical and observational access across the Pilot window.

Evidence: None obtained.

Owner: Site leadership

Participating crewsNOT_READY

Requirement: Named mechanical, electrical and instrumentation crews committed to Pilot journeys.

Evidence: None obtained.

Owner: Construction management

Discipline supervisionNOT_READY

Requirement: Supervisors available and briefed for each discipline.

Evidence: None obtained.

Owner: Discipline superintendents

Real lookahead informationNOT_READY

Requirement: Live 2–3 week lookahead for the CV-07 corridor.

Evidence: None obtained (P6 NOT_CONNECTED).

Owner: Project Controls

Planned Job CardsNOT_READY

Requirement: Real concurrent Job Cards planned within the corridor.

Evidence: None obtained.

Owner: Work Control

Equipment contextNOT_READY

Requirement: Tag / system / energy-state context for the corridor.

Evidence: None obtained.

Owner: Commissioning

Work windowsNOT_READY

Requirement: Agreed windows that do not disturb mandatory production/control processes.

Evidence: None obtained.

Owner: Site leadership

Shift availabilityNOT_READY

Requirement: Coverage across the shifts in which journeys occur.

Evidence: None obtained.

Owner: Construction management

Agreed observational protocolNOT_READY

Requirement: Consented observation, recording and privacy protocol.

Evidence: None obtained.

Owner: Product Ownership + IR

Non-disruption confirmationNOT_READY

Requirement: Written confirmation the Pilot cannot disrupt mandatory production/control processes.

Evidence: None obtained.

Owner: Operations authority

H · BEFORE Measurement Readiness — twelve frozen metrics

M-01 · Time to determine work-package readiness.NOT_READY

Start → End: Supervisor begins readiness check. → Readiness conclusion reached.

Source / Method: Field observation · Timed observation

Owner / Availability: UNASSIGNED · Requires field access — NOT_AVAILABLE.

ExclusionRule: Exclude interruptions unrelated to readiness.

M-02 · Time to identify the binding blocker.NOT_READY

Start → End: Readiness check begins. → Binding blocker named correctly.

Source / Method: Field observation · Timed observation

Owner / Availability: UNASSIGNED · NOT_AVAILABLE

ExclusionRule: Exclude cases with no blocker.

M-03 · Number of systems consulted per readiness decision.NOT_READY

Start → End: Check begins. → Decision reached.

Source / Method: Field observation · Count

Owner / Availability: UNASSIGNED · NOT_AVAILABLE

ExclusionRule: Exclude systems opened for unrelated work.

M-04 · Duplicate data entry events per shift.NOT_READY

Start → End: Shift start. → Shift end.

Source / Method: Field observation · Count

Owner / Availability: UNASSIGNED · NOT_AVAILABLE

ExclusionRule: Exclude corrections of user error.

M-05 · Document search time per package.NOT_READY

Start → End: Search begins. → Correct revision confirmed.

Source / Method: Field observation · Timed observation

Owner / Availability: UNASSIGNED · NOT_AVAILABLE (Aconex NOT_CONNECTED).

ExclusionRule: Exclude searches for non-mandatory documents.

M-06 · First-Pass Readiness rate.NOT_READY

Start → End: Crew arrives at work front. → Work starts or is aborted.

Source / Method: Work Control records · Ratio

Owner / Availability: UNASSIGNED · NOT_AVAILABLE — source interface not validated.

ExclusionRule: Exclude weather-only stand-downs.

M-07 · Aborted mobilisations per week.NOT_READY

Start → End: Crew mobilises. → Work abandoned before start.

Source / Method: Supervisor log · Count

Owner / Availability: UNASSIGNED · NOT_AVAILABLE — source interface not validated.

ExclusionRule: Exclude reassignments not caused by readiness.

M-08 · Lead time from blocker arising to blocker detection.NOT_READY

Start → End: Condition becomes invalid. → Owner becomes aware.

Source / Method: Source timestamps · Interval

Owner / Availability: UNASSIGNED · NOT_AVAILABLE — source interface not validated.

ExclusionRule: Exclude conditions never relevant to planned work.

M-09 · SIMOPS conflicts identified before execution day.NOT_READY

Start → End: Lookahead publication. → Execution day.

Source / Method: Planning records · Count

Owner / Availability: UNASSIGNED · NOT_AVAILABLE — source interface not validated.

ExclusionRule: Exclude conflicts outside the corridor.

M-10 · Rework attributable to invalid or superseded conditions.NOT_READY

Start → End: Work executed. → Rework raised.

Source / Method: Quality records · Count + attribution

Owner / Availability: UNASSIGNED · NOT_AVAILABLE — source interface not validated.

ExclusionRule: Exclude design-change rework.

M-11 · Time to reconstruct the basis of a past decision.NOT_READY

Start → End: Evidence request raised. → Complete basis assembled.

Source / Method: Audit exercise · Timed exercise

Owner / Availability: UNASSIGNED · NOT_AVAILABLE — source interface not validated.

ExclusionRule: Exclude requests outside the corridor.

M-12 · Escalations required to obtain an authorization decision.NOT_READY

Start → End: Authorization requested. → Decision issued or refused.

Source / Method: Work Control records · Count

Owner / Availability: UNASSIGNED · NOT_AVAILABLE — source interface not validated.

ExclusionRule: Exclude escalations caused by absence unrelated to the Pilot.

The twelve approved BEFORE metrics remain unchanged. Measurement must begin prospectively; a baseline must never be reconstructed retrospectively after the Pilot has begun.

I · Offline / Reconciliation Readiness

OfflineCaptureNOT_READY

Requirement: Field capture continues without connectivity, marked as capture only.

Demonstrated: Prototype behaviour only; no Pilot device build exists.

BaseVersionNOT_READY

Requirement: Every offline record pins the source versions it was based on.

Demonstrated: Designed; not demonstrated on Pilot mechanism.

ImmutablePendingQueueNOT_READY

Requirement: Queued items cannot be edited to appear authorized.

Demonstrated: Designed; not demonstrated.

ReconnectNOT_READY

Requirement: Deterministic resynchronisation on reconnect.

Demonstrated: Not demonstrated.

ConflictDetectionNOT_READY

Requirement: Base-version drift detected and surfaced, never auto-merged.

Demonstrated: Not demonstrated.

ReconciliationNOT_READY

Requirement: Human reconciliation with attribution.

Demonstrated: Not demonstrated.

RecoveryVerificationNOT_READY

Requirement: SERVICE_RESTORED is distinguished from OPERATIONALLY_RECOVERED.

Demonstrated: Not demonstrated.

OFFLINE NEVER AUTHORIZES.

The offline Pilot journey is classified NOT_EXECUTABLE_IN_CURRENT_PILOT. Successful offline behaviour will not be simulated and presented as Pilot evidence.

§13 · Phase 6A Readiness Register

GC-01 Enterprise Interface Validation
BLOCKINGNOT_READY

RequiredEvidence: Per-source validated participation mode with owner-issued evidence artefact.

EvidenceObtained: None (6 of 6 sources unvalidated).

Owner: Enterprise system owners + Integration governance

ResidualRisk: Decisions would rest on unproven source behaviour — false READY risk.

Disposition: HOLD until each mandatory-decision source holds a validated participation mode.

GC-02 Enterprise IAM / Identity
BLOCKINGNOT_READY

RequiredEvidence: Server-side identity, role, scope, delegation and expiry enforcement with denial evidence.

EvidenceObtained: None — prototype identity only.

Owner: Enterprise IAM owner + ES&H

ResidualRisk: Unattributable authorization; audit reconstruction would fail.

Disposition: HOLD — no real authorization journey may execute.

GC-03 ADR-15 / ADR-17 Pilot Authority & Lifecycle
BLOCKINGNOT_READY

RequiredEvidence: Lifecycle and transition authority resolved for Job Card and Temporary Modification in CV-07.

EvidenceObtained: None — both objects UNRESOLVED.

Owner: Enterprise Work Control authority

ResidualRisk: State changes without an accountable owner.

Disposition: HOLD or formally reduce Pilot scope in writing.

GC-04 Stewardship & Change Readiness
BLOCKINGNOT_READY

RequiredEvidence: Named assignment, authority, availability, backup and escalation for 7 roles.

EvidenceObtained: None — all roles unstaffed; P3-TRN-01 unfunded.

Owner: Project / site leadership

ResidualRisk: Design-team dependency would be structurally guaranteed.

Disposition: HOLD — dependent capabilities remain DISABLED_SAFE.

GC-05 CA-04 Governed Classification / Retention
BLOCKINGNOT_READY

RequiredEvidence: Approved classification, compensability and retention per evidence class.

EvidenceObtained: None — all four entries CLASSIFICATION_UNRESOLVED.

Owner: Legal / records governance + ES&H

ResidualRisk: Compensability decided by technical default — constitutional violation.

Disposition: HOLD and fail closed where materially required.

Critical Control participation (Path A or Path B)
BLOCKINGNOT_READY

RequiredEvidence: Real governed participation, or a written rescope to SIMULATED_ONLY / NON_ACCEPTANCE_EVIDENCE.

EvidenceObtained: None — remains SIMULATED with no governance decision.

Owner: Critical Control functional owner

ResidualRisk: Simulated control mistaken for real integration evidence.

Disposition: HOLD — Life-Critical journey not executable as evidence.

Design-team-withdrawn test readiness
BLOCKINGNOT_READY

RequiredEvidence: Support and escalation paths staffed and exercised without design-team involvement.

EvidenceObtained: None — no organizational roles to withdraw from.

Owner: Operational Support + Product Ownership

ResidualRisk: Sustainability result would be predetermined and meaningless.

Disposition: HOLD until GC-04 is closed.

Field / operational prerequisites
BLOCKINGNOT_READY

RequiredEvidence: Access, crews, supervision, lookahead, Job Cards, equipment context, windows, shifts, observation protocol, non-disruption confirmation.

EvidenceObtained: None of 10 confirmed.

Owner: Site leadership

ResidualRisk: Pilot could disturb mandatory production/control processes.

Disposition: HOLD.

BEFORE measurement readiness
BLOCKINGNOT_READY

RequiredEvidence: Twelve metrics instrumented, owned and capturing prospectively before activation.

EvidenceObtained: None — 12 of 12 NOT_READY, no owners assigned.

Owner: Project Controls + Product Ownership

ResidualRisk: Retrospective baseline reconstruction would invalidate all value claims.

Disposition: HOLD — start prospective capture first.

Offline / reconciliation preconditions
BLOCKINGNOT_READY

RequiredEvidence: Demonstrated capture, base-version pinning, immutable queue, conflict detection, reconciliation and recovery verification.

EvidenceObtained: None demonstrated on a Pilot mechanism.

Owner: Integration Support + Product Ownership

ResidualRisk: Simulated success could mask an unauthorized offline authorization path.

Disposition: Offline journey classified NOT_EXECUTABLE_IN_CURRENT_PILOT.

Frozen Pilot Definition Baseline integrity
READY

RequiredEvidence: Baseline reproduced unchanged; any change classified and logged.

EvidenceObtained: Baseline verified unchanged; 0 change requests logged.

Owner: Product Ownership

ResidualRisk: None at this stage.

Disposition: READY — integrity maintained.

Architecture Drift Register active
READY_WITH_CONTROL

RequiredEvidence: Drift triggers defined and monitored against the Technical Architecture Baseline.

EvidenceObtained: Register active; no Pilot implementation exists to compare, therefore no variance recorded.

Owner: Enterprise Architecture

ResidualRisk: Drift can only be assessed once implementation begins.

Disposition: Carry into Phase 6B.

K · Pre-execution failure test (6A-11)

FT-01 · Missing / unvalidated enterprise interface behind a mandatory condition.PASS

Expected: Condition marked UNRESOLVED; readiness verdict HOLD; never READY by omission.

Observed: Readiness engine returns HOLD with the unresolved source named as the attributable blocker.

Note: Verified against the prototype engine, not against a live source. Behaviour is design-level evidence only.

FT-02 · Unresolved identity attempting a confirmation action.PASS

Expected: Action denied; AuthorityResolutionState = UNRESOLVED; no HUMAN_CONFIRMED record written.

Observed: Confirmation is refused and no evidence record is created.

Note: Prototype identity only — enterprise IAM enforcement remains unevidenced (GC-02 open).

FT-03 · Vacant mandatory steward for a dependent capability.PASS

Expected: Dependent capability DISABLED_SAFE; no silent fallback to another role.

Observed: Capability reports DISABLED_SAFE with the vacant role named.

Note: All seven roles are currently vacant, so the test is trivially satisfied and must be re-run once staffed.

FT-04 · Conflicting federation mapping for the same source object.PASS_WITH_FINDING

Expected: SEMANTIC_PROPOSAL only; never consumed by the decision engine; mapping steward escalation raised.

Observed: Conflict surfaced as an unresolved mapping; decision path fails closed.

Note: No FederationMappingSteward exists to receive the escalation — the escalation terminates nowhere (GC-04 open).

FT-05 · Unavailable Critical Control source during a Life-Critical evaluation.PASS_WITH_FINDING

Expected: STOP / HOLD; absence of a life-critical control is never compensable.

Observed: Evaluation returns STOP with a non-compensable critical blocker.

Note: Source is SIMULATED, so the test proves engine logic, not source governance. No integration claim may be made.

FT-06 · Unsupported offline state attempting to authorize work.NOT_EXECUTED

Expected: Authorization refused offline; OFFLINE NEVER AUTHORIZES preserved; capture queued as pending only.

Observed: No offline authorization path exists in the Pilot mechanism; the journey is NOT_EXECUTABLE_IN_CURRENT_PILOT.

Note: Explicitly not simulated as executed evidence; impact recorded against Pilot acceptance.

Fail-closed behaviour is confirmed at engine level for five of six provocations, and the sixth is formally declared non-executable rather than simulated. This confirms the design does not depend on optimistic assumptions, but it does NOT close any GC condition: every provocation was exercised against prototype/simulated sources, so it is design evidence, not enterprise evidence.

B · Phase 6A Evidence Closure Register

CLOSED 1CLOSED_WITH_CONTROL 2REMAINS_OPEN 9NOT_APPLICABLE 1

Readiness is never averaged. Any single blocking condition that REMAINS_OPEN keeps Phase 6B on HOLD.

GC-01 · Enterprise interface validation (Q4, Aconex, P6, Smart Completions/BCSTools, Critical Control, HR/RRLL, Training, Health, IAM)
BLOCKINGREMAINS_OPEN

OriginalState: NOT_YET_VALIDATED

RequiredClosureEvidence: Owner-issued validation artefact per source: mechanism, read/write/event capability, version and failure behaviour.

EvidenceObtained: None. No source system owner has issued a validation artefact.

CompetentOwner: Enterprise system owners + Integration governance

ActualState: NOT_YET_VALIDATED

ResidualRisk: Mandatory Pilot decisions would rest on unproven source behaviour.

GC-02 · Enterprise IAM / identity / authority enforcement
BLOCKINGREMAINS_OPEN

OriginalState: NOT_YET_VALIDATED

RequiredClosureEvidence: Server-side enforcement evidence for authorized, unauthorized, expired, delegated, unresolved and vacant-authority actors.

EvidenceObtained: Prototype-level denial behaviour only (FT-02); no enterprise identity source connected.

CompetentOwner: Enterprise IAM owner + ES&H

ActualState: UNRESOLVED

ResidualRisk: Unattributable authorization; evidence reconstruction would fail.

GC-03 · ADR-15 / ADR-17 Pilot lifecycle and transition authority (Job Card, Temporary Modification)
BLOCKINGREMAINS_OPEN

OriginalState: UNRESOLVED

RequiredClosureEvidence: Named lifecycle owner and transition authority for each CV-07 object, with unavailable-authority behaviour.

EvidenceObtained: None; fail-closed default (HOLD/STOP) preserved but unowned.

CompetentOwner: Enterprise Work Control authority

ActualState: UNRESOLVED

ResidualRisk: State changes without an accountable authority.

GC-04 · ADR-14 stewardship staffing + P3-TRN-01 change adoption
BLOCKINGREMAINS_OPEN

OriginalState: UNRESOLVED

RequiredClosureEvidence: Named resource, authority, availability, delegate and escalation for all seven mandatory roles.

EvidenceObtained: None. 7 of 7 roles vacant; dependent capabilities DISABLED_SAFE (FT-03).

CompetentOwner: Project / site leadership

ActualState: UNRESOLVED

ResidualRisk: Design-team dependency structurally guaranteed; stewardship test meaningless.

GC-05 · CA-04 governed classification, compensability and retention
BLOCKINGREMAINS_OPEN

OriginalState: UNRESOLVED

RequiredClosureEvidence: Approved classification and retention per evidence class, with authority basis and effective date.

EvidenceObtained: None. All entries CLASSIFICATION_UNRESOLVED and failing closed as non-compensable.

CompetentOwner: Legal / records governance + ES&H

ActualState: CLASSIFICATION_UNRESOLVED

ResidualRisk: Compensability could be decided by implementation convenience.

PRC-01 · Critical Control participation (Path A real, or Path B formal rescope)
BLOCKINGREMAINS_OPEN

OriginalState: SIMULATED

RequiredClosureEvidence: Governed source participation evidence, or a signed rescope classifying the Life-Critical journey SIMULATED_ONLY / NON_ACCEPTANCE_EVIDENCE.

EvidenceObtained: None. No competent authority decision has been taken on either path.

CompetentOwner: Critical Control functional owner

ActualState: SIMULATED

ResidualRisk: Simulated control mistaken for real integration evidence.

PRC-02 · Design-team-withdrawn support model executable
BLOCKINGREMAINS_OPEN

OriginalState: UNRESOLVED

RequiredClosureEvidence: Staffed L1/L2/L3 path, escalation chain, excluded-activity list and emergency exception rule exercised without the design team.

EvidenceObtained: Model defined; no organizational roles exist to withdraw from.

CompetentOwner: Operational Support + Product Ownership

ActualState: UNRESOLVED (dependent on GC-04)

ResidualRisk: Sustainability verdict would be predetermined.

PRC-03 · Field / operational prerequisites for CV-07
BLOCKINGREMAINS_OPEN

OriginalState: NOT_YET_VALIDATED

RequiredClosureEvidence: Confirmed locations, crews, supervision, lookahead, Job Cards, windows, equipment context, observation protocol and interference control.

EvidenceObtained: 0 of 10 confirmed.

CompetentOwner: Site leadership

ActualState: NOT_YET_VALIDATED

ResidualRisk: Pilot could interfere with mandatory operational controls.

PRC-04 · BEFORE measurement prospective start (12 frozen metrics)
BLOCKINGREMAINS_OPEN

OriginalState: NOT_YET_MEASURED

RequiredClosureEvidence: Each metric instrumented, owned, with declared source, method, exclusion rule and prospective collection start date.

EvidenceObtained: None. 12 of 12 NOT_READY; no owners assigned; no collection started.

CompetentOwner: Project Controls + Product Ownership

ActualState: NOT_YET_MEASURED

ResidualRisk: Retrospective baseline reconstruction would invalidate every value claim.

PRC-05 · Offline / reconciliation Pilot capability
CLOSED_WITH_CONTROL

OriginalState: NOT_YET_VALIDATED

RequiredClosureEvidence: Demonstrated capture, base-version pinning, immutable queue, conflict detection, reconciliation and recovery verification on the Pilot mechanism.

EvidenceObtained: Not demonstrated. Explicitly classified rather than simulated (FT-06).

CompetentOwner: Integration Support + Product Ownership

ActualState: NOT_EXECUTABLE_IN_CURRENT_PILOT

ResidualRisk: Offline journey cannot contribute Pilot acceptance evidence; J-offline will be NOT_EXECUTED_WITH_REASON.

PRC-06 · Frozen Pilot Definition Baseline integrity
CLOSED

OriginalState: FROZEN

RequiredClosureEvidence: Baseline reproduced unchanged; every change request classified and logged.

EvidenceObtained: All 17 baseline elements reproduced unchanged; 0 change requests logged.

CompetentOwner: Product Ownership

ActualState: FROZEN — INTACT

ResidualRisk: None at this stage.

PRC-07 · Pre-execution failure test (6A-11)
CLOSED_WITH_CONTROL

OriginalState: NOT_YET_VALIDATED

RequiredClosureEvidence: Six governed provocations exercised with expected fail-closed responses.

EvidenceObtained: 5 exercised (3 PASS, 2 PASS_WITH_FINDING), 1 NOT_EXECUTED and formally classified.

CompetentOwner: Enterprise Architecture + ES&H

ActualState: DESIGN_EVIDENCE_ONLY

ResidualRisk: Results were obtained against prototype/simulated sources and must be re-run against validated interfaces.

PRC-08 · Architecture Drift Register active for Pilot
NOT_APPLICABLE

OriginalState: NOT_APPLICABLE (no implementation)

RequiredClosureEvidence: Drift triggers defined and monitored against the four governing baselines.

EvidenceObtained: Register active; no Pilot implementation exists to compare.

CompetentOwner: Enterprise Architecture

ActualState: ACTIVE — NO VARIANCE RECORDED

ResidualRisk: Drift only assessable once implementation begins.

DISP · Phase 6A — formal disposition (received)

STATUS: HOLDPHASE 6A ACCEPTED AS CORRECTLY EXECUTEDCONTROLLED PILOT EXECUTION NOT AUTHORIZED

1 CLOSED · 2 CLOSED_WITH_CONTROL · 1 NOT_APPLICABLE · 9 REMAINS_OPEN (BLOCKING)

BlockingNature: The nine blocking conditions are accepted as genuine Pilot-entry dependencies, not design defects. They are external readiness obligations owned outside the design team.

6A-11 FailureTest: The 6A-11 pre-execution failure test is accepted as evidence that the prototype/design preserves fail-closed behaviour. It closes no enterprise readiness condition because it was executed against prototype/simulated sources rather than validated production-participating sources: DesignEvidence ≠ PilotReadinessEvidence.

Offline: NOT_EXECUTABLE_IN_CURRENT_PILOT is accepted. Offline success must not be simulated to satisfy the Pilot Definition. The impact of this non-executed journey remains visible and must be carried into the eventual Phase 6 acceptance decision.

BaselineIntegrity: 17/17 frozen elements unchanged · 0 change requests · 0 STRUCTURAL_REOPEN_REQUIRED · no redesign requested

Phase 6B: NOT COMMENCED — outputs D–T remain unpopulated until a future Phase 6A rerun reaches formal GO

Phase 7: NO_GO — ENTRY CONDITION NOT MET. No Phase 7 production-readiness conclusion may be inferred from this result.

NextAuthorizedStep: PHASE 6A BLOCKING CONDITION CLOSURE WORKSTREAM — limited to the nine blocking conditions

W · Blocking condition closure workstream (9 conditions)

TOTAL 9READY FOR RETEST 0PARTIAL 1NO NEW EVIDENCE 8

0 conditions are ready for retest on evidence. PRC-01 is retestable on a competent-authority decision alone (Path A or Path B), which changes classification but does not by itself create Pilot readiness. Phase 6A GO/HOLD therefore remains HOLD and is not re-run.

GC-01 — Enterprise Interface ValidationRETEST: NO — NO NEW EVIDENCE

CurrentBlockingState: NOT_YET_VALIDATED — 0 of 9 source systems have issued an owner-signed validation artefact; all remain NOT_CONNECTED or SIMULATED.

RequiredExternalAction: Each source-system owner (Q4, Aconex, P6, Smart Completions/BCSTools, Critical Control, HR/RRLL, Training, Health, IAM) confirms in writing the integration mechanism, read/write/event capability, object scope, version/pinning behaviour, latency class and declared failure behaviour for the CV-07 Pilot scope.

CompetentOwner: Enterprise System Owners (per source) with Integration Governance as convener

EvidenceRequired: Signed per-source Interface Validation Record + a connectivity test log against the Pilot environment demonstrating the declared failure behaviour (unavailable, stale, unmapped state).

TargetClosureState: VALIDATED (read scope) with any write-back explicitly OUT_OF_PILOT_SCOPE or separately validated.

Dependency: GC-02 (identity propagation for authenticated reads); PRC-01 for Critical Control specifically.

EscalationPath: Integration Governance → Enterprise Architecture Authority → Project Sponsor

ClosureEvidenceRef: PENDING — /interface-validation/GC-01/*

GC-02 — Enterprise IAM / Identity & Authority EnforcementRETEST: NO — NO NEW EVIDENCE

CurrentBlockingState: UNRESOLVED — only prototype-level denial behaviour exists (FT-02); no enterprise identity source is connected and no server-side enforcement is attributable.

RequiredExternalAction: Enterprise IAM owner provisions Pilot identities, role/authority claims, delegation and revocation, and confirms server-side enforcement of authorized, unauthorized, expired, delegated, unresolved and vacant-authority actors.

CompetentOwner: Enterprise IAM Owner, co-signed by ES&H for safety-authority claims

EvidenceRequired: IAM integration record + enforcement test evidence for the six actor classes + attributable identity present in a reconstructed decision record.

TargetClosureState: ENFORCED_SERVER_SIDE with attributable identity on every authorization event.

Dependency: GC-03 (authority claims must map to lifecycle transition authority); GC-04 (steward identities must exist to be granted).

EscalationPath: IAM Owner → ES&H Authority → Enterprise Architecture Authority → Project Sponsor

ClosureEvidenceRef: PENDING — /iam/GC-02/enforcement-evidence

GC-03 — ADR-15 / ADR-17 Lifecycle & Transition AuthorityRETEST: NO — NO NEW EVIDENCE

CurrentBlockingState: UNRESOLVED — Job Card and Temporary Modification lifecycle ownership and transition authority are unassigned; the system holds fail-closed but unowned.

RequiredExternalAction: Enterprise Work Control authority names the lifecycle owner and transition authority for each CV-07 object class and ratifies the behaviour when that authority is unavailable.

CompetentOwner: Enterprise Work Control Authority (with ES&H concurrence for Temporary Modification)

EvidenceRequired: Signed ADR-15 / ADR-17 closure record listing object class, lifecycle owner, transition authority, delegation rule and unavailable-authority behaviour.

TargetClosureState: RESOLVED — authority assigned per object class; unavailable authority remains fail-closed (HOLD/STOP), never auto-advance.

Dependency: GC-02 (authority must be technically enforceable); GC-04 (named humans must exist).

EscalationPath: Work Control Authority → ES&H Authority → Project Sponsor

ClosureEvidenceRef: PENDING — /adr/ADR-15-17-closure

GC-04 — ADR-14 Stewardship Staffing + P3-TRN-01RETEST: NO — NO NEW EVIDENCE

CurrentBlockingState: UNRESOLVED — 7 of 7 mandatory stewardship roles vacant; dependent capabilities fail closed as DISABLED_SAFE (FT-03).

RequiredExternalAction: Project/site leadership appoints all seven mandatory stewards with named resource, authority basis, availability commitment, named delegate and escalation route, and funds the P3-TRN-01 change-adoption load.

CompetentOwner: Project / Site Leadership (accountable), Product Ownership (register custodian)

EvidenceRequired: Completed stewardship assignment register (7/7 named + delegates) + committed availability + P3-TRN-01 adoption plan with resourced training and change-load capacity.

TargetClosureState: STAFFED — 7/7 assigned with delegates; DISABLED_SAFE capabilities re-enabled under named authority.

Dependency: Blocks PRC-02 (design-team-withdrawn support) and the entire stewardship sustainability test in Phase 6B.

EscalationPath: Site Leadership → Project Director → Project Sponsor

ClosureEvidenceRef: PENDING — /stewardship/ADR-14-assignment-register

GC-05 — CA-04 Governed Classification, Compensability & RetentionRETEST: NO — NO NEW EVIDENCE

CurrentBlockingState: CLASSIFICATION_UNRESOLVED — every evidence class fails closed as non-compensable with no approved retention basis.

RequiredExternalAction: Legal/records governance with ES&H approves, per evidence class, the governed classification, compensability (never compensable by default), retention period, authority basis and effective date.

CompetentOwner: Legal / Records Governance + ES&H Authority

EvidenceRequired: Approved classification and retention schedule per evidence class, with authority basis, effective date and change-control route.

TargetClosureState: GOVERNED_CLASSIFICATION_APPROVED — compensability decided by competent authority, never by implementation convenience.

Dependency: Constrains evidence reconstruction scope in GC-01 and audit retention in Phase 7 Section legal certification.

EscalationPath: Records Governance → Legal Counsel → ES&H Authority → Project Sponsor

ClosureEvidenceRef: PENDING — /governance/CA-04-classification-schedule

PRC-01 — Critical Control Participation (Path A / Path B)RETEST: PARTIAL — DECISION ONLY

CurrentBlockingState: SIMULATED — no competent-authority decision has been taken on either path; the Life-Critical journey has no governed source.

RequiredExternalAction: Critical Control functional owner formally elects Path A (real governed participation for the Pilot) or Path B (signed rescope classifying the Life-Critical journey SIMULATED_ONLY / NON_ACCEPTANCE_EVIDENCE).

CompetentOwner: Critical Control Functional Owner, countersigned by ES&H Authority

EvidenceRequired: Path A: source participation record + validated interface per GC-01. Path B: signed rescope decision stating that no Life-Critical acceptance evidence may be inferred from the Pilot.

TargetClosureState: PARTICIPATING (Path A) or FORMALLY_RESCOPED (Path B) — never silently simulated.

Dependency: Path A depends on GC-01 and GC-02; Path B changes the evidentiary weight of Phase 6 acceptance.

EscalationPath: Critical Control Owner → ES&H Authority → Project Sponsor

ClosureEvidenceRef: PENDING — /critical-control/path-decision

PRC-02 — Design-Team-Withdrawn Support ReadinessRETEST: NO — NO NEW EVIDENCE

CurrentBlockingState: UNRESOLVED — the support model is defined but no organizational roles exist to withdraw the design team from.

RequiredExternalAction: Operational Support and Product Ownership staff the L1/L2/L3 path, publish the escalation chain and excluded-activity list, and rehearse the emergency exception rule with the design team absent.

CompetentOwner: Operational Support Lead + Product Ownership

EvidenceRequired: Staffed support roster, escalation chain, excluded-activity list, and a rehearsal log showing resolution without design-team involvement.

TargetClosureState: EXECUTABLE_WITHOUT_DESIGN_TEAM.

Dependency: Hard-dependent on GC-04 (stewards must exist before support can be withdrawn).

EscalationPath: Support Lead → Product Ownership → Project Director

ClosureEvidenceRef: PENDING — /support/withdrawal-rehearsal-log

PRC-03 — Field / Operational Prerequisites (CV-07)RETEST: NO — NO NEW EVIDENCE

CurrentBlockingState: NOT_YET_VALIDATED — 0 of 10 field prerequisites confirmed for the AREA-3100 / TT01 corridor scope.

RequiredExternalAction: Site leadership confirms locations, crews, supervision, lookahead horizon, Job Card population, work windows, equipment context, observation protocol, interference control and SIMOPS exposure for the frozen CV-07 scope.

CompetentOwner: Site Leadership (Construction/Commissioning), with ES&H for observation and interference control

EvidenceRequired: Signed field prerequisite checklist (10/10) + confirmed observation protocol that cannot interfere with mandatory operational controls.

TargetClosureState: FIELD_CONFIRMED (10/10) for the frozen scope — scope must not be shrunk to obtain the confirmation.

Dependency: PRC-04 (BEFORE measurement must start in the same confirmed scope).

EscalationPath: Site Leadership → Construction Manager → Project Director

ClosureEvidenceRef: PENDING — /field/CV-07-prerequisite-checklist

PRC-04 — Prospective BEFORE Measurement ReadinessRETEST: NO — NO NEW EVIDENCE

CurrentBlockingState: NOT_YET_MEASURED — 12 of 12 frozen metrics NOT_READY; no owners assigned; no prospective collection has started.

RequiredExternalAction: Project Controls instruments each of the 12 frozen metrics with a named owner, declared source, collection method, exclusion rule and a prospective start date preceding any Pilot journey.

CompetentOwner: Project Controls + Product Ownership

EvidenceRequired: Per-metric instrumentation record + evidence that collection began prospectively (dated) before Phase 6B, with no retrospective reconstruction.

TargetClosureState: BEFORE_MEASUREMENT_ACTIVE — a defensible pre-Pilot baseline exists for all 12 metrics.

Dependency: PRC-03 (scope must be field-confirmed first); determines whether any Phase 6B value claim is attributable.

EscalationPath: Project Controls → Product Ownership → Project Director

ClosureEvidenceRef: PENDING — /measurement/before-baseline-register

  • Scope is limited to the nine blocking conditions. Phase 6A is not re-run in full until evidence has materially changed.
  • Only conditions whose ReadyForRetest is YES may be retested; retesting without new external evidence produces no closure.
  • No condition may be closed because the architecture provides a technical solution for it — closure requires attributable external evidence from a competent owner.
  • Conditions are non-compensable: strong closure in one condition never offsets an open condition elsewhere.
  • Scope must never be reduced in order to convert a blocking condition into a closed one; scope reduction is a SCOPE_CHANGE against the frozen baseline.
  • Once all mandatory blockers are closed or formally dispositioned, rerun the Phase 6A GO/HOLD determination in full; Phase 6B may begin only after formal GO authorization.

STAGE 2 · Phase 6B controlled pilot execution — gate

STAGE 1 = HOLDNOT_COMMENCED — PHASE 6B REGISTERS DELIBERATELY UNPOPULATED

The closure prompt requires strict stage separation: Phase 6B may begin only after Stage 1 reaches GO — CONTROLLED PILOT EXECUTION AUTHORIZED and a formal authorization is issued. Stage 1 result is HOLD with nine blocking conditions REMAINS_OPEN, so no journey register, BEFORE/AFTER evidence, SIMOPS field result, continuity result, forecast result, workaround finding, stewardship verdict, value claim or Option C sustainability verdict has been produced. Producing them now would be fabrication, not evidence.

Withheld Phase 6B outputs

  • D. Phase 6B Pilot Execution Executive Summary
  • E. 20-Journey Execution Register (J-01…J-20)
  • F. BEFORE / AFTER Evidence
  • G. SIMOPS Field Verification
  • H. Location Continuity Verification
  • I. Forecast Readiness Verification
  • J. Change / Reassessment Verification
  • K. Offline / Recovery Verification
  • L. Field / Workaround Findings
  • M. Stewardship Sustainability Test
  • N. Value & Causal Attribution Register
  • O. Option C Sustainability Assessment (remains NOT_YET_DETERMINABLE)
  • P. Architecture Drift Register results
  • Q. Operational / Technical Incident Register
  • S. Pilot Acceptance Register
  • T. Final Phase 6 Disposition Recommendation

No STRUCTURAL_REOPEN_REQUIRED condition was raised: closure was attempted without adding architecture, changing engine contracts, redefining domain semantics or altering no-compensation, Location governance, SIMOPS semantics or authority boundaries.

Phase 7 remains NO_GO — ENTRY CONDITION NOT MET.

L · Residual Risk Register

P6A-R-01 · Pressure to execute Pilot journeys against simulated sources to demonstrate progress.HIGH

Control: Journeys with an unvalidated mandatory source are NOT_EXECUTABLE as evidence; simulated results are non-acceptance evidence by rule.

P6A-R-02 · Retrospective BEFORE baseline reconstruction after Pilot start.HIGH

Control: Prospective capture is a hard precondition; any retrospective baseline invalidates the value register.

P6A-R-03 · Stewardship staffed nominally by the design team, hiding the sustainability question.HIGH

Control: DesignTeamExcludedActivities list plus emergency-exception logging.

P6A-R-04 · Silent weakening of the Life-Critical journey instead of a formal rescope decision.HIGH

Control: Path A / Path B are the only permitted outcomes; both require competent authority.

P6A-R-05 · Manual data copying presented as federation.MEDIUM

Control: CONTROLLED_MANUAL_FEDERATION must be declared explicitly with an owner and failure behaviour; copying is never LIVE_READ.

P6A-R-06 · Compensability decided by technical default while CA-04 is unresolved.HIGH

Control: CLASSIFICATION_UNRESOLVED fails closed as non-compensable.

K · GO / HOLD recommendation

GC-01 through GC-05 closed to Pilot scope

All five remain OPEN with no closure evidence.

NOT MET

Mandatory interfaces validated

0 of 6 sources hold a validated participation mode.

NOT MET

Real identity / authority available

Enterprise IAM NOT_CONNECTED; identity unresolved.

NOT MET

Pilot-required lifecycle authority resolved

ADR-15 / ADR-17 unresolved for Job Card and Temporary Modification.

NOT MET

Stewardship roles staffed

7 of 7 mandatory roles unassigned.

NOT MET

Field access confirmed

0 of 10 field prerequisites evidenced.

NOT MET

BEFORE measurement can start prospectively

No metric instrumented or owned.

NOT MET

Critical Control participation real or formally rescoped

Remains SIMULATED; no governance decision taken.

NOT MET

Offline journey executable or formally classified non-executable

Formally classified NOT_EXECUTABLE_IN_CURRENT_PILOT — no simulated success claimed.

MET

No Critical unresolved precondition exists

Ten blocking preconditions remain unresolved.

NOT MET
HOLD

Phase 6A does not achieve GO. Nine of ten GO criteria are unmet and ten blocking preconditions remain unresolved. Controlled Pilot Execution (Phase 6B) is therefore NOT AUTHORIZED, and none of the twenty frozen journeys may be executed. The frozen Pilot Definition Baseline remains intact and must not be adjusted to close this gap.

Required to lift the HOLD

  • Evidence-backed participation mode for every mandatory-decision source (GC-01).
  • Enterprise identity, role and delegation enforcement with denial evidence (GC-02).
  • Resolved Job Card and Temporary Modification lifecycle authority for CV-07 (GC-03).
  • Named, mandated and covered stewardship for all seven roles plus funded P3-TRN-01 (GC-04).
  • Approved CA-04 classification, compensability and retention decisions (GC-05).
  • Path A or Path B decision for Critical Control participation.
  • Confirmed field access, crews, windows and observation protocol.
  • Prospective BEFORE measurement running before activation.

PHASE 6B — CONTROLLED PILOT EXECUTION: NOT COMMENCED. It begins only after a formal GO — CONTROLLED PILOT EXECUTION AUTHORIZED. No Phase 6B register (journeys, BEFORE/AFTER, SIMOPS, continuity, forecast, offline, adoption, sustainability, value, drift) may be populated before that authorization, and none has been.