PizarraContexto de trabajoDocumentos y registrosControles críticosRegistrosPreparaciónCondiciones bloqueantesAutorización
Aseguramiento / Técnico
READY2

All mandatory conditions verified

CONDITIONAL2

Releasable only with stated conditions

HOLD7

Required condition not satisfied

STOP1

Active work must cease

No compensation rule. No overall weighted readiness percentage is produced. A satisfied Engineering gate never offsets an unsatisfied critical control, permit, authority or evidence condition.

Today / Next Shift — Work Readiness

Drill down for the decision context, source versions and evidence behind each state.

Work PackageActivityWBSAreaPlanned StartFrontES&HCritical ConditionRestrictionOwnerRequired ByOperational State
MCC-1 cable termination — EL +12 m
WP-1001 · SWPP-301
Electrical installation at height using MEWPWBS-2.4.1Area 200 — Process2026-08-30 07:00:00ZSATISFIEDSATISFIEDNone openNone
READYONLINE
Pipe rack spool installation — Line 2140-PL-12
WP-1002 · SWPP-302
Mechanical installation with mobile crane liftWBS-2.4.2Area 200 — Process2026-08-30 07:00:00ZNOT SATISFIEDSATISFIEDNone openClient release letter CRL-0442 not issued; tie-in window not confirmed.Client Interface Manager2026-08-30 05:00:00Z
HOLDONLINE
Transformer bay earthing installation
WP-1003 · SWPP-303
Electrical earthing works in energised substation zoneWBS-2.4.3Area 200 — Process2026-08-30 07:00:00ZSATISFIEDNOT SATISFIEDCC-021 UNAVAILABLERequired critical control not available/verified/effective — Verified isolation and earthing applied before workES&H Supervisor2026-08-30 05:00:00Z
HOLDONLINE
Confined space vessel internals cleaning — V-2210
WP-1004 · SWPP-304
Confined space entry and internal cleaningWBS-2.4.4Area 200 — Process2026-08-30 07:00:00ZSATISFIEDNOT SATISFIEDCC-031 FAILEDCritical control lost during execution — Continuous atmospheric monitoring activeES&H SupervisorImmediate
STOPexec: STOPONLINE
Instrument loop check — Subsystem 2140-02
WP-1005 · SWPP-305
Loop checking and functional verificationWBS-2.4.5Area 200 — Process2026-08-30 07:00:00ZSATISFIEDCONDITIONALNone openControlled document revision pending materiality assessmentEngineering Manager2026-08-30 08:00:00Z
HOLDexec: REASSESSONLINE
Cable tray modification — Area 300 rack B
WP-1006 · SWPP-306
Structural / electrical support modificationWBS-2.4.6Area 300 — Utilities2026-08-30 07:00:00ZSATISFIEDUNVERIFIABLENone openUnable to verify required condition — Aconex unavailable since 2026-08-29T19:50Z; freshness of ACX-STD-0025 cannot be established.Document Control2026-08-30 05:00:00Z
HOLDSOURCE UNAVAILABLE
Grounding grid continuity testing — Area 100
WP-1007 · SWPP-307
Field testing with offline evidence captureWBS-2.4.7Area 100 — Intake2026-08-30 07:00:00ZSATISFIEDSATISFIEDNone openNone
READYexec: CONTINUEOFFLINE
Valve actuator alignment — Subsystem 2160-01
WP-1008 · SWPP-308
Mechanical alignment and functional strokeWBS-2.4.8Area 200 — Process2026-08-30 07:00:00ZSATISFIEDNOT SATISFIEDNone openUnresolved reconciliation on JHA record — evidence chain cannot be certified.Document Control2026-08-30 05:00:00Z
HOLDCONFLICT
Hot work — structural weld repair, Area 300
WP-1009 · SWPP-309
Hot work welding in classified areaWBS-2.4.9Area 300 — Utilities2026-08-30 07:00:00ZSATISFIEDCONDITIONALNone openPermit approval routed to active delegate DLG-0031 within valid scope.ES&H Manager
CONDITIONALONLINE
Pump P-2170 sanction to test — motor solo run
WP-1010 · SWPP-310
Energisation and solo run under Sanction to TestWBS-2.4.10Area 200 — Process2026-08-30 07:00:00ZSATISFIEDCONDITIONALNone openSIMOPS interface with WP-1011 requires zone coordination before energisation.General Foreman
CONDITIONALONLINE
Adjacent cable pulling — SIMOPS with P-2170 test
WP-1011 · SWPP-311
Cable pulling adjacent to live test zoneWBS-2.4.11Area 200 — Process2026-08-30 07:00:00ZNOT SATISFIEDSATISFIEDNone openZone access release for SIMOPS window not granted.Client Interface Manager2026-08-30 05:00:00Z
HOLDONLINE
Excavation for duct bank — Area 100 corridor
WP-1012 · SWPP-312
Mechanical excavation near buried servicesWBS-2.4.12Area 100 — Intake2026-08-30 07:00:00ZSATISFIEDNOT SATISFIEDNone openSpotter qualification QUAL-EXC-02 expired 2026-08-15; no qualified substitute assigned.General Foreman2026-08-30 05:00:00Z
HOLDONLINE

Mandatory demonstration scenarios

Each demonstration scenario is represented by a live package in the register above.

Scenario 01 — Fully ReadyREADY
MCC-1 cable termination — EL +12 m

Every mandatory condition is satisfied and verified against its authoritative source. No compensation was applied.

Decision owner
Area Superintendent
Scenario 02 — ES&H Ready / Client Release MissingHOLD
Pipe rack spool installation — Line 2140-PL-12

Every ES&H gate is satisfied. Client Release is outstanding, which is non-compensable, so the integrated state is HOLD and ownership stays with the Client Interface Manager.

Decision owner
Client Interface Manager
Scenario 03 — Front Ready / Critical Control MissingHOLD
Transformer bay earthing installation

Front Readiness is fully green. A required critical control is unavailable, so no aggregate score may release the work — HOLD.

Decision owner
ES&H Supervisor
Scenario 04 — Critical Control Lost During ExecutionSTOP
Confined space vessel internals cleaning — V-2210

Work was released and started. Continuous atmospheric monitoring failed in the field. Active work must cease: STOP, followed by reassessment.

Decision owner
ES&H Supervisor
Scenario 05 — New Controlled Document RevisionHOLD
Instrument loop check — Subsystem 2140-02

Aconex published a new revision after release. The pinned baseline was not silently replaced; a materiality assessment is pending, so the package sits CONDITIONAL / REASSESS.

Decision owner
Engineering Manager
Scenario 06 — Aconex UnavailableHOLD
Cable tray modification — Area 300 rack B

The document authority source is unavailable. The governed snapshot covers two of three mandatory documents; freshness for the third cannot be established, so the package is HOLD — Unable to Verify Required Condition.

Decision owner
Document Control
Scenario 07 — Offline Field OperationREADY
Grounding grid continuity testing — Area 100

The crew is operating outside coverage on the approved offline package. Local evidence capture is permitted and queued as immutable events.

Decision owner
Area Superintendent
Scenario 08 — Sync ConflictHOLD
Valve actuator alignment — Subsystem 2160-01

An offline device event and a server-side change diverge from the same base version. No Last-Write-Wins: the divergence is preserved as RECONCILIATION REQUIRED and routed to the accountable authority.

Decision owner
Document Control
Scenario 09 — Mandatory Approver UnavailableCONDITIONAL
Hot work — structural weld repair, Area 300

The mandatory Permit Authorizer is unavailable. A valid delegate exists within scope, so the decision routes to the delegate rather than being bypassed.

Decision owner
ES&H Manager
Scenario 10 — Q4 Sanction to TestCONDITIONAL
Pump P-2170 sanction to test — motor solo run

An approved Sanction to Test links isolation, equipment and work package. Adjacent construction work in the same zone becomes CONDITIONAL under SIMOPS.

Decision owner
General Foreman
Scenario 11 — Saved Time Not CapturedHOLD
Adjacent cable pulling — SIMOPS with P-2170 test

Package preparation was 35 minutes faster than baseline, but a concurrent client release restriction blocks execution. Time Saved ≠ Productive Time Captured.

Decision owner
Client Interface Manager
Scenario 12 — AI Suggestion Rejected (+ expired competency)HOLD
Excavation for duct bank — Area 100 corridor

An AI applicability proposal was rejected by a competent reviewer; the proposal, its basis and the human decision are all retained. An expired competency independently drives HOLD.

Decision owner
General Foreman