PizarraContexto de trabajoDocumentos y registrosControles críticosRegistrosPreparaciónCondiciones bloqueantesAutorización
Aseguramiento / Técnico

Macro C — Corporate Industrialization & Operational Transition

PH6A-FPSO-MPC-REV0 · industrialize correctly without promoting evidence class

HANDOVER READYPHASE 6A HOLDPHASE 7 NO GO
Macro status
CORPORATE_HANDOVER_READY_OPERATIONAL_EVIDENCE_PENDING
Handover baseline
PH6A-CORPORATE-DEVELOPMENT-HANDOVER-REV0
G-FPSO-08
PASS
G-PH6A
HOLD
External dependencies
18 (0 closed · 1 under validation · 17 open)
Blocking BCs
9
Highest evidence class
SIMULATION_EVIDENCE
Controlled pilot
NOT AUTHORIZED

§0 Execution authority — independently reconstructed

MacroPromptC_Authorized verified, not assumed

CheckObservedVerdict
MacroPromptC_Authorized asserted by parent macrotruePASS
Parent macro status is ACCEPTED (not inferred)ACCEPTEDPASS
Scenario baseline FROZENFROZENPASS
G-FPSO-07 demonstrator acceptance gatePASSPASS
Operational boundary carried unchanged from parentHOLD / PROHIBITEDPASS

B. Governing configuration lineage

§1 · superseded baselines are historical evidence only

KeyBaselineStatus
ArchitectureBaselinePH6A-IADA-REV1FROZEN AND SEALED
ArchitectureSealPH6A-IADA-REV1-SEAL-01ACTIVE AND FROZEN
CorporateInteractionArchitecturePH6A-BXIA-REV0ACCEPTED
FunctionalBaselinePH6A-FPSO-FUNCTIONAL-BASELINE-REV1FROZEN
InteractionDesignPH6A-FPSO-IAD-REV2ACCEPTED
BechtelizedApplicationBaselinePH6A-FPSO-BAC-REV0ACCEPTED
PrototypePH6A-FPSO-PROTOTYPE-REV0BUILD COMPLETE
ImplementationConformancePH6A-FPSO-ICV-REV0ACCEPTED
FunctionalVerificationPH6A-FPSO-FVT-REV0PASS
ApplicationEngineeringBaselinePH6A-FPSO-APPLICATION-ENGINEERING-BASELINE-REV0VERIFIED
ScenarioBaselinePH6A-FPSO-SCENARIO-BASELINE-REV0FROZEN
DemonstratorPH6A-FPSO-E2E-DEMO-REV0EXECUTED
DemonstratorAssurancePH6A-FPSO-DAA-REV0ACCEPTED
SimulationEvidenceACCEPTEDSIMULATION CLASS ONLY
InheritedExternalDependencyCount15CARRIED FORWARD

NO_IMPLEMENTATION_FROM_SUPERSEDED_BASELINE = TRUE · PH6A-FPSO-FUNCTIONAL-BASELINE-REV0 — historical evidence only · PH6A-FPSO-IAD-REV1 — historical evidence only · PH6A-FPSO-FUNCTIONAL-BASELINE-REV1-CANDIDATE — superseded by REV1 FROZEN

§2–4 Operational boundary, evidence law and stage model

Preserved boundary

OperationalClosureEvidenceNOT YET ACQUIRED
Phase6AHOLD
Phase6BNOT AUTHORIZED
Phase7NO GO
BC09ProtectionACTIVE
PilotExposurePROHIBITED

Fundamental evidence law

  • DesignEvidence ≠ OperationalClosureEvidence
  • SoftwareVerificationEvidence ≠ OperationalClosureEvidence
  • SimulationEvidence ≠ OperationalClosureEvidence
  • DocumentExists ≠ OperationalClosure
  • OwnerNamed ≠ OwnerValidated
  • MockIntegration ≠ LiveIntegration
  • PrototypeBehaviour ≠ ProductionBehaviour
  • TechnicalReadiness ≠ OrganizationalAuthorization

Stage execution

C1 Corporate Development HandoverEXECUTED
C2 Phase 6A Operational RevalidationEXECUTED RESULT HOLD
C3 Controlled PilotNOT EXECUTED ENTRY UNMET
C4 Production ReadinessNOT EXECUTED ENTRY UNMET
C5 Production Release & Operational HandoverNOT EXECUTED ENTRY UNMET

C. Corporate development handover package

§7 · PH6A-CORPORATE-DEVELOPMENT-HANDOVER-REV0 · 33 mandatory artefacts

IDContentSource baselineCompletenessNote
H-01ArchitectureBaselinePH6A-IADA-REV1COMPLETE14 logical components, 12 hardened contract families.
H-02ArchitectureSealPH6A-IADA-REV1-SEAL-01COMPLETE4 logical locks active; provenance PRV-01…PRV-18.
H-03ArchitectureDecisionRecordsADR-01…ADR-24COMPLETE WITH OPEN DEPENDENCYADR-03, ADR-13/CA-01, ADR-15…24 remain controlled-open.
H-04FunctionalRequirementsOfRecordPH6A-FPSO-FUNCTIONAL-BASELINE-REV1COMPLETEFC-FPSO-01…08, 38-element schema each.
H-05InteractionDesignPH6A-FPSO-IAD-REV2COMPLETE16 screens S01–S16; 18-step field journey.
H-06BechtelizedApplicationSpecificationPH6A-FPSO-BAC-REV0COMPLETE17 conformance dimensions; F-IAD-03 controlled non-blocking.
H-07PrototypeReferencePH6A-FPSO-PROTOTYPE-REV0COMPLETEReference implementation of the deterministic PureCore only.
H-08SemanticDictionaryPH6A-IADA-REV1COMPLETEGoverned term set; corporate implementation may not re-define terms.
H-09CapabilityModelPH6A-FPSO-AIA-REV0COMPLETE26 assessed capabilities; 24 implemented in PureCore.
H-10FactModelPH6A-AHP-REV1.1COMPLETE6 fact classes AUTHORITATIVE…AUTHORIZED_DECISION; 9 invariants.
H-11StateModelsPH6A-FPSO-FCD-REV0COMPLETE60 states, 33 transitions, 55 reason codes.
H-12DecisionRightsModelPH6A-IADA-REV1COMPLETE WITH OPEN DEPENDENCYModel complete; actual corporate assignments are OWNER_VALIDATION_REQUIRED.
H-13AuthorityBoundaryPH6A-IADA-REV1COMPLETEPermission ≠ Authority; system consumes authority, never manufactures it.
H-14SourceAuthorityRegisterMPC §FCOMPLETE WITH OPEN DEPENDENCYObject-specific; all entries owner-evidence dependent.
H-15InterfaceContractRegisterMPC §ECOMPLETE WITH OPEN DEPENDENCY10 candidate systems, all mock-only today.
H-16TemporalValidityModelXR-TEMP-01 / REM-REV0COMPLETEEvaluationTimestamp is a governed input.
H-17TIME_EVENT_CHANGE_DEMAND TriggerModelPH6A-IADA-REV1COMPLETEFour trigger classes drive all revalidation.
H-18ConcurrencyModelPH6A-SADR-REM-REV0COMPLETERow-level optimistic concurrency guards.
H-19IdempotencyModelPH6A-FPSO-FCD-REV0COMPLETEEvent keys per device/object/baseVersion.
H-20DigitalSignatureAssuranceModelFC-FPSO-08 / REM-REV0COMPLETE WITH OPEN DEPENDENCYSignatureEvidence immutable vs SignatureApplicability evaluated; legal sufficiency unproven.
H-21OfflineAndRecoveryModelPH6A-IADA-REV1COMPLETE WITH OPEN DEPENDENCYEXT-15 offline signature reconciliation authority remains open.
H-22FailureContainmentModelPH6A-FPSO-FVT-REV0COMPLETEFail-closed on unverifiable mandatory condition.
H-23SecurityConstraintsMPC §40EVIDENCE REQUIREDCorporate cybersecurity approval not obtained.
H-24PrivacyConstraintsMPC §24COMPLETEDecision-fact exposure only; no health/HR detail.
H-25AuditAndProvenanceModelSEAL-01 / IADACOMPLETEReconstructable decision lineage.
H-26GovernedOperationalEventModelPH6A-IADA-REV1COMPLETEEvent-sourced, immutable, no last-write-wins.
H-27AIContainmentBoundaryPH6A-AHP-REV1.1COMPLETEAI-to-Rule firewall; SEMANTIC_PROPOSAL never consumed by IRDE.
H-28VerificationBaselinePH6A-FPSO-ICV-REV0 + FVT-REV0COMPLETE24/24 ICV, 30 FVT executed.
H-29SimulationEvidencePH6A-FPSO-DAA-REV0COMPLETEClassified SIMULATION_EVIDENCE; non-promotable.
H-30ExternalDependencyRegisterMPC §HCOMPLETE WITH OPEN DEPENDENCY18 dependencies after reconciliation.
H-31OpenFindingRegisterMPC §AJCOMPLETE6 material findings, 0 critical uncontrolled.
H-32CorporateImplementationAcceptanceCriteriaMPC §JCOMPLETECIAC-01…CIAC-14.
H-33ConfigurationLineageMPC §BCOMPLETE15 lineage rows, superseded baselines flagged historical.

D. Capability industrialization classification

§8 · 26 capabilities · 0 classified PRODUCTION_READY

IDCapabilityContractClassificationRationale
CAP-01Location acquisition & confirmationFC-FPSO-01
REFERENCE IMPLEMENTATIONPRODUCTION IMPLEMENTATION REQUIRED
GPS is an input signal only; human confirmation remains the authority act. GPS ≠ Authority.
CAP-02Location replacement / re-confirmationFC-FPSO-01
REFERENCE IMPLEMENTATIONOWNER VALIDATION REQUIRED
Replacement invalidates dependent context; Location authority owner unvalidated.
CAP-03Contextual document retrievalFC-FPSO-02
EXTERNAL INTEGRATION REQUIREDPROTOTYPE ONLY
Aconex API availability unproven; retrieval currently mock.
CAP-04Revision election (no automatic election)FC-FPSO-02
REFERENCE IMPLEMENTATIONOWNER VALIDATION REQUIRED
Document-status authority must be validated with the document owner.
CAP-05Pre-start preventive package compositionFC-FPSO-03
REFERENCE IMPLEMENTATIONCONFIGURATION REQUIRED
Applicability rules are configuration per project/area.
CAP-06SYSTEM_PROPOSED vs HUMAN_CONFIRMED separationFC-FPSO-03
REFERENCE IMPLEMENTATION
Semantics frozen; corporate build must preserve exactly.
CAP-07Crew confirmation & role-slot inheritanceFC-FPSO-04
REFERENCE IMPLEMENTATIONEXTERNAL INTEGRATION REQUIRED
Competency/fitness decision facts require live sources.
CAP-08Competency validity gatingFC-FPSO-04
EXTERNAL INTEGRATION REQUIREDOWNER VALIDATION REQUIRED
Authoritative competency source unvalidated (ADR-04 open).
CAP-09Fitness decision fact consumptionFC-FPSO-04
CORPORATE POLICY DECISION REQUIRED
Privacy minimization requires a corporate decision on the exposed fact.
CAP-10IPERC Continuo (continuous risk assessment)FC-FPSO-05
REFERENCE IMPLEMENTATIONCONFIGURATION REQUIRED
Hazard/control taxonomy is enterprise configuration.
CAP-11Field delta assessment & REASSESS triggerFC-FPSO-06
REFERENCE IMPLEMENTATION
Deterministic trigger model verified by FVT.
CAP-12Tool / equipment readiness & expiryFC-FPSO-07
EXTERNAL INTEGRATION REQUIREDOWNER VALIDATION REQUIRED
Tool source-of-record unidentified; expiry facts unverifiable today.
CAP-13Digital signature capture (evidence)FC-FPSO-08
PROTOTYPE ONLYPRODUCTION IMPLEMENTATION REQUIRED
Prototype captures evidence; PKI/credential mechanism absent.
CAP-14Signature applicability evaluationFC-FPSO-08
REFERENCE IMPLEMENTATION
Applicability recomputed against current object version.
CAP-15Offline signature reconciliationFC-FPSO-08
OWNER VALIDATION REQUIREDCORPORATE POLICY DECISION REQUIRED
EXT-15 open: no competent authority defined for offline reconciliation.
CAP-16Temporal validity enforcement (XR-TEMP-01)Cross-contract
REFERENCE IMPLEMENTATION
No material decision may rely on a temporally expired fact.
CAP-17Critical control availability & failureCross-contract
EXTERNAL INTEGRATION REQUIREDOWNER VALIDATION REQUIRED
Enterprise critical-control authority cannot be established by prototype configuration.
CAP-18Permit / isolation state consumptionCross-contract
EXTERNAL INTEGRATION REQUIRED
Q4/Engica read-only integration unproven.
CAP-19SIMOPS compositional evaluationCross-contract
REFERENCE IMPLEMENTATIONCONFIGURATION REQUIRED
CUM-1…CUM-7 rules frozen; matrices are configuration.
CAP-20Authority resolution & delegationCross-contract
OWNER VALIDATION REQUIREDEXTERNAL INTEGRATION REQUIRED
Decision rights must come from IAM + corporate authority register.
CAP-21Offline minimum safe information setCross-contract
REFERENCE IMPLEMENTATIONPRODUCTION IMPLEMENTATION REQUIRED
Cache freshness governance requires production storage design.
CAP-22Event-sourced sync & conflict reconciliationCross-contract
REFERENCE IMPLEMENTATIONPRODUCTION IMPLEMENTATION REQUIRED
No last-write-wins; production needs durable event store.
CAP-23Audit / provenance reconstructionCross-contract
REFERENCE IMPLEMENTATIONPRODUCTION IMPLEMENTATION REQUIRED
Retention and log protection are enterprise obligations.
CAP-24AI advisory containmentCross-contract
REFERENCE IMPLEMENTATIONCORPORATE POLICY DECISION REQUIRED
Data residency / model governance is a corporate decision (ADR-09).
CAP-25Prospective value measurement captureCross-contract
CONFIGURATION REQUIREDOWNER VALIDATION REQUIRED
BC09 protection active; BEFORE baseline not started.
CAP-26Production observability & alertingCross-contract
PRODUCTION IMPLEMENTATION REQUIRED
Not in prototype scope; no NFR targets defined.

E. Corporate interface contract register

§9 · no API or interface capability fabricated

IDBusiness objectCandidate system / roleRead / WriteFreshness · DependencyFailure / Offline / ReconciliationValidationCompetent ownerEvidence of closure
IF-01Controlled document / procedure / PETS
Aconex
CANDIDATE_SYSTEM_OF_RECORD
REQUIRED / NONE
Per-shift or on CHANGE event
BLOCKING
Snapshot UNVERIFIABLE → fail closed on mandatory document
Pinned authorized snapshot with governed validity window
Revision delta → materiality assessment, no auto-election
EVIDENCE REQUIREDCorporate Document Control ManagerAPI capability statement + document authority confirmation
IF-02Identity / role / session
Corporate IAM
CANDIDATE_IDENTITY_SOURCE
REQUIRED / NONE
Real-time; session-bounded
BLOCKING
No authenticated identity → no material decision
Cached identity with bounded validity; no new authority
Stale role → revalidate on reconnect
EVIDENCE REQUIREDCorporate IAM OwnerAuthentication mechanism + role/permission model evidence
IF-03Permit / work authorization
Q4 / Engica
CANDIDATE_SYSTEM_OF_RECORD
REQUIRED / NONE
Event-driven
BLOCKING
Permit state unverifiable → HOLD
Read-only cached state, no permit creation
Server state authoritative on reconnect
EVIDENCE REQUIREDWork Control Process OwnerIntegration feasibility + ownership confirmation (ADR-01/02)
IF-04Isolation / sanction to test
Q4 / Engica
CANDIDATE_SYSTEM_OF_RECORD
REQUIRED / NONE
Event-driven
BLOCKING
Fail closed
No offline isolation change
Server authoritative
EVIDENCE REQUIREDElectrical / Energy Isolation AuthorityIsolation object contract + authority confirmation
IF-05Critical control / fatal-risk taxonomy
Forwood
CANDIDATE_SYSTEM_OF_RECORD
REQUIRED / NONE
Daily + on change
BLOCKING
Unverifiable critical control → HOLD (no contingency verification)
Cached verification status with expiry
Verification recency re-evaluated
EVIDENCE REQUIREDCorporate ES&H Critical Control OwnerBC06 Path A/B decision + source authority confirmation
IF-06Competency / qualification
People & Training
CANDIDATE_SOURCE
REQUIRED (decision fact) / NONE
Daily
BLOCKING
Competency unverifiable → person not assignable to gated role
Cached validity with hard expiry (XR-TEMP-01)
Expiry recomputed at EvaluationTimestamp
EVIDENCE REQUIREDTraining & Competency ManagerAuthoritative source designation + fact-level interface
IF-07Fitness decision
Occupational Health decision service
CANDIDATE_SOURCE
DECISION FACT ONLY / NONE
Shift-bounded
BLOCKING
NOT_CONFIRMED → not assignable
Shift-scoped cached decision fact
Re-fetch each shift
EVIDENCE REQUIREDOccupational Health Lead + Data Privacy OfficerMinimized fact contract approval
IF-08Tool / equipment certification
UNIDENTIFIED
CANDIDATE_SOURCE_UNKNOWN
REQUIRED / NONE
On use + expiry watch
BLOCKING
Expired/unverifiable certification → tool not usable
Cached certificate expiry
Expiry recomputed
EVIDENCE REQUIREDEquipment / Plant ManagerSystem identification + interface capability statement
IF-09Location / area / SIMOPS context
Readiness Layer (owned) + project master data
SYSTEM_OF_RECORD_FOR_DECISION_CONTEXT
OWNED / OWNED
Continuous
BLOCKING
Location unconfirmed → no pre-start progression
Full offline confirmation with sync
Event-sourced
UNDER VALIDATIONLocation Data Steward (vacant)Named, accepted stewardship assignment
IF-10Schedule / WBS / look-ahead
Primavera P6
CANDIDATE_SYSTEM_OF_RECORD
REQUIRED / NONE
Daily
DEGRADABLE
Look-ahead degraded; field work unaffected
Cached look-ahead
Overwrite from source
EVIDENCE REQUIREDProject Controls ManagerExtract contract + refresh cadence agreement
  • ConnectedSystem ≠ AuthoritativeSystem
  • CandidateSource ≠ SystemOfRecord
  • RetrievedFact ≠ AuthoritativeFact
  • SourceAuthority is OBJECT_SPECIFIC and OWNER_EVIDENCE_DEPENDENT

F. Source authority register

§10 / §20 · object-specific and owner-evidence dependent

ObjectCandidate systemAuthority claimedEvidenceStatus
DocumentAconexCANDIDATENone admittedEVIDENCE REQUIRED
WorkPackage / JobCardQ4 / EngicaCANDIDATENone admittedEVIDENCE REQUIRED
LocationReadiness LayerCANDIDATEDesign only; steward vacantUNDER VALIDATION
IdentityCorporate IAMCANDIDATENone admittedEVIDENCE REQUIRED
CompetencyPeople & TrainingCANDIDATENone admitted (ADR-04 open)EVIDENCE REQUIRED
TrainingPeople & TrainingCANDIDATENone admittedEVIDENCE REQUIRED
FitnessDecisionOccupational Health serviceCANDIDATENone admittedEVIDENCE REQUIRED
ToolUNIDENTIFIEDNONENo candidate systemEVIDENCE REQUIRED
EquipmentUNIDENTIFIEDNONENo candidate systemEVIDENCE REQUIRED
RestrictionUndetermined (ADR-03 open)NONEADR-03 unresolvedEVIDENCE REQUIRED
CriticalControlForwoodCANDIDATENone admitted; BC06 path undecidedEVIDENCE REQUIRED
PermitQ4 / EngicaCANDIDATENone admittedEVIDENCE REQUIRED
IsolationQ4 / EngicaCANDIDATENone admittedEVIDENCE REQUIRED
SignatureCorporate PKI (undetermined)NONENo credential mechanism evidencedEVIDENCE REQUIRED
SchedulePrimavera P6CANDIDATENone admittedEVIDENCE REQUIRED

G. Decision rights / authority register

§19 · OwnerNamed ≠ OwnerValidated

RoleMaterial decisionScopeNamed partyValidationEvidence required
AccountableAuthorize pre-start release of work at a locationProject × Area × ShiftConstruction Superintendent (role only)OWNER NAMED NOT VALIDATEDSigned decision-rights confirmation with effective period
OwnerOwn the integrated readiness decision contextProjectNot assignedUNASSIGNEDCorporate product/service ownership assignment
StewardMaintain Location & SIMOPS master dataAreaVacant (scenario G-01)UNASSIGNEDNamed steward + accepted terms of reference (ADR-14)
ApproverApprove permit / work authorizationArea × Activity × RiskExternal (Q4 authority)OWNER NAMED NOT VALIDATEDConfirmation that approval authority remains external and is not mirrored
ExecutorConfirm location and crew at the work frontLocation × ShiftCrew Lead (role only)OWNER NAMED NOT VALIDATEDRole-to-decision-right mapping accepted by line management
CustodianCustody of signature and audit evidenceEnterpriseNot assignedUNASSIGNEDRecords custody assignment + retention class
EscalationResolve HOLD/STOP escalation out of hoursProject × ShiftNot assignedUNASSIGNEDEscalation matrix with effective periods
DelegateAct for an unavailable approverScoped delegationNot assignedUNASSIGNEDDelegation policy + revocation mechanism evidence
  • DecisionRight is never inferred from role
  • DecisionRight is never inferred from system permission
  • DecisionRight is never inferred from competency
  • DecisionRight is never inferred from signature
  • DecisionRight is never inferred from prior approval

H. External dependency register

§27 · inherited 15 → independently reconstructed 18

Inherited
15
Reconstructed
18
New in Macro C
EXT-16, EXT-17, EXT-18
Closed
0
Under validation
1
Open
17
IDAffected capabilityRequired decisionCompetent ownerCurrent evidenceSafe interim behaviourClosure predicateStatus
EXT-01Document retrieval (CAP-03)Aconex API availability and extract scopeCorporate Document Control ManagerNoneMandatory document unverifiable → HOLDDocumented API capability + agreed extract contractOPEN
EXT-02Document authority (CAP-04)Who holds document-status authorityDocument Control ManagerNoneNo automatic revision electionNamed authority confirms status semanticsOPEN
EXT-03Identity & session (CAP-20)Corporate IAM authentication mechanismIAM OwnerNoneNo material decision without authenticated identityIAM integration pattern acceptedOPEN
EXT-04Decision rights (CAP-20)Source of decision rights and delegationProject Director + IAM OwnerNoneAuthorityResolutionState = UNRESOLVED → fail closedAuthoritative decision-rights register existsOPEN
EXT-05Permit / isolation (CAP-18)Q4/Engica read integration feasibilityWork Control Process OwnerNonePermit state unverifiable → HOLDIntegration feasibility confirmed in writingOPEN
EXT-06Critical control (CAP-17)Forwood integration or formal rescope (BC06 Path A/B)Corporate ES&HNoneCritical control SIMULATED → not usable for releasePath A evidence or recorded Path B rescopeOPEN
EXT-07Competency (CAP-08)Authoritative competency source (ADR-04)Training & Competency ManagerNoneUnverifiable competency → role not assignableSource designated and interface agreedOPEN
EXT-08Fitness decision (CAP-09)Minimized fitness fact contractOccupational Health + Privacy OfficerNoneNOT_CONFIRMED defaultPrivacy-approved fact contractOPEN
EXT-09Tool readiness (CAP-12)Identify tool/equipment system of recordEquipment ManagerNoneUnverifiable certification → tool unusableSystem identified with interface capabilityOPEN
EXT-10Signature credential (CAP-13)Credential / PKI mechanismCorporate SecurityNoneSignature evidence captured but no legal claim madeCredential mechanism approvedOPEN
EXT-11Signature legal sufficiency (CAP-13)Legal sufficiency of digital signatureLegal CounselNoneNo DigitalNotary / LegallyBinding claimLegal opinion issuedOPEN
EXT-12Location stewardship (CAP-02)Named Location data steward (ADR-14)Project DirectorRole defined, party vacantLocation change requires manual verificationNamed steward accepts terms of referenceUNDER VALIDATION
EXT-13Restriction authority (CAP-19)Authoritative restriction system (ADR-03)Project Controls + ES&HNoneRestrictions treated as non-compensable blockersADR-03 decided with owner evidenceOPEN
EXT-14Prospective measurement (CAP-25)BEFORE measurement baseline start authorizationProject DirectorNoneBC09Protection ACTIVE; no pilot exposureProspective collection formally underwayOPEN
EXT-15Offline signature reconciliation (CAP-15)Authority to reconcile signatures captured offline against a changed object versionCorporate Legal + Work Control Process OwnerNone — not material to the primary demonstrationOffline signature whose object version changed → SignatureApplicability LOST, decision re-requiredNamed authority defines offline reconciliation rules and evidenceOPEN
EXT-16All production capabilities (CAP-26)Corporate development organization accepting industrializationCorporate IT / Digital DeliveryNoneHandover package remains READY_TO_ENGAGE onlyNamed delivery organization accepts the handover packageOPEN
EXT-17Security constraints (H-23)Cybersecurity approval of the target solution patternCorporate CybersecurityNoneNo production environment; prototype isolated with synthetic dataSecurity review completed with dispositionOPEN
EXT-18Non-functional requirements (§39)SLA / SLO / RTO / RPO / retention targetsService Owner (unassigned)NoneClassified REQUIREMENT_REQUIRED_FROM_COMPETENT_OWNER; nothing inventedNFR set issued by competent ownerOPEN

New IDs assigned only for dependencies created by corporate industrialization scope; no historical ID reused or renumbered.

I. EXT-15 explicit disposition

§11 · mandatory carry-forward

Dependency
EXT-15 — Offline Signature Reconciliation Authority
Status
OPEN EXTERNAL DEPENDENCY
Materiality in demonstration
NOT_MATERIAL — the frozen scenario did not exercise offline signature divergence
Safe interim behaviour
SignatureApplicability is recomputed against the current object version; divergence loses applicability and re-requires the decision.

Present in

  • CorporateHandover (H-20, H-21)
  • OperationalRevalidation (§Q)
  • SignatureGovernance
  • OfflineModel
  • ProductionReadiness (deferred, entry unmet)

Explicitly excluded from any scope-based filtering; it may not disappear because it was not demonstrated.

J. Corporate implementation acceptance criteria

§12–13 · technology may differ, semantics may not

SameGovernedFacts ∧ SameRuleVersions ∧ SameConfiguration ∧ SameEvaluationTimestamp ∧ SameDecisionRights ⇒ MateriallyEquivalentDecision

IDCriterionVerification methodNon-compensable
CIAC-01Material semantics of FC-FPSO-01…08 preserved regardless of technologyContract clause conformance reviewYES
CIAC-02Equivalence predicate holds against the reference PureCore for a governed test corpusDifferential execution vs reference implementationYES
CIAC-03EvaluationTimestamp is a governed input, never an implicit system clock read inside rulesCode and design review + temporal test setYES
CIAC-04XR-TEMP-01 enforced: no material decision relies on a temporally expired factTemporal adversarial test suiteYES
CIAC-05EffectiveFrom / ValidUntil / RevalidationTrigger / DecisionImpact retained on every temporal factData model reviewYES
CIAC-06No-compensation logic preserved: no weighted or averaged readiness scoreDecision engine reviewYES
CIAC-07Permission ≠ Authority enforced; decision rights consumed, never inferredAuthority test suiteYES
CIAC-08SignatureEvidence immutable and separated from evaluated SignatureApplicabilitySignature lifecycle testYES
CIAC-09SYSTEM_PROPOSED never consumed as HUMAN_CONFIRMED by any ruleAI/rule firewall testYES
CIAC-10Fail-closed behaviour on unverifiable mandatory conditionsFailure containment testYES
CIAC-11Event-sourced sync with reconciliation; no last-write-winsConcurrency and offline testYES
CIAC-12Idempotent event intake under retry and duplicate deliveryIdempotency testNO
CIAC-13Full decision reconstruction from persisted provenanceAudit reconstruction exerciseYES
CIAC-14Rule versions explicitly recorded on every persisted decisionDecision record schema reviewYES

K. Requirement-to-handover traceability

§14 · TraceabilityBreaks = 0

Architecture requirementContractClauseInteractionPrototypeVerificationSimulationAcceptance criterion
AR-LOC-01 Location context inheritanceFC-FPSO-01CL-01.4 confirmation actS03 Location ConfirmationconfirmLocation()ICV-R04 / FVT-03T2–T3CIAC-01
AR-DOC-02 No automatic revision electionFC-FPSO-02CL-02.7 electionS05 Document SetelectRevision()ICV-R07 / FVT-08T6CIAC-01
AR-PKG-03 Proposal vs confirmation separationFC-FPSO-03CL-03.5S07 Preventive PackageconfirmPackageItem()ICV-R09 / FVT-11T8CIAC-09
AR-CRW-04 Role-slot inheritanceFC-FPSO-04CL-04.6S09 Crew ConfirmationassignRoleSlot()ICV-R12 / FVT-14T10CIAC-07
AR-RSK-05 IPERC continuoFC-FPSO-05CL-05.3S11 IPERCevaluateIperc()ICV-R15 / FVT-18T12CIAC-06
AR-DLT-06 Field delta reassessmentFC-FPSO-06CL-06.2S13 Delta AssessmentassessFieldDelta()ICV-R18 / FVT-21T16–T18CIAC-10
AR-TOL-07 Tool temporal validityFC-FPSO-07CL-07.4S14 Tool ReadinessevaluateToolValidity()ICV-R21 / FVT-25T19CIAC-04
AR-SIG-08 Signature evidence vs applicabilityFC-FPSO-08CL-08.5 / CL-08.9S16 SignaturecaptureSignature() / evaluateSignatureApplicability()ICV-R24 / FVT-29T20–T21CIAC-08
AR-TMP-09 Temporal coherence (XR-TEMP-01)Cross-contractXR-TEMP-01All screensevaluationTimestamp guardTADV-01…08T17CIAC-03 / CIAC-04
AR-AUT-10 Permission ≠ AuthorityCross-contractAUTH-INV-3All decision actionsresolveDecisionRight()ICV-R02T11CIAC-07
AR-SIM-11 SIMOPS compositional rulesCross-contractCUM-1…CUM-7S04 SIMOPS ContextevaluateSimops()ICV-R06 / FVT-06T15CIAC-06
AR-OFF-12 Offline & recoveryCross-contractOFF-INV-2S15 Offline QueuequeueEvent() / reconcile()ICV-R23T14CIAC-11

L. G-FPSO-08 — corporate development handover readiness

§15

PredicateValueBasis
BaselineLineageCompleteTRUE15 lineage rows reconstructed; superseded baselines flagged historical.
FunctionalRequirementsOfRecordCompleteTRUEFC-FPSO-01…08 at FUNCTIONAL-BASELINE-REV1, 38-element schema each.
InterfaceBoundariesExplicitTRUE10 candidate systems with read/write/freshness/failure/offline behaviour.
AuthorityBoundaryExplicitTRUEAuthority register + 5 inference prohibitions.
SourceAuthorityUncertaintyExplicitTRUENo object claims validated source authority.
OpenDependenciesPreservedTRUEEXT-15 explicitly carried forward; 18 dependencies preserved.
PrototypeVsProductionBoundaryExplicitTRUENo capability classified PRODUCTION_READY.
AcceptanceCriteriaDefinedTRUECIAC-01…CIAC-14 with verification methods.
NoUnsupportedAuthorityClaimTRUEAll authority rows are NAMED_NOT_VALIDATED or UNASSIGNED.
NoUnsupportedIntegrationClaimTRUEAll external systems remain candidates; no API fabricated.
NoEvidenceClassPromotionTRUEDesign/verification/simulation evidence remains at its own class.
TraceabilityBreaks = 0TRUE12 chains complete architecture → acceptance criterion.
G-FPSO-08 PASSMeans READY_TO_ENGAGE_CORPORATE_DEVELOPMENT · does NOT mean CORPORATE_ACCEPTANCE

M. Operational evidence admission register

§17–18 · existing evidence infrastructure preserved, not replaced

ComponentStatusNote
/oei — Owner Evidence IntakePRESERVEDQuestionnaire baseline PH6A-W1-OEAVQ-REV1 frozen; 7-check assessment intact.
/board — Operational Evidence Execution BoardPRESERVED28 evidence requests ER-01…ER-28.
/erx — Evidence Request ExchangePRESERVEDWave 1 requests linked.
/bcw — Blocking Condition Closure WorkstreamPRESERVEDBC-01…BC-09 in three frozen Mesa packages.
External dependency registerEXTENDEDExtended by MPC to 18 entries; no historical entry altered.
Owner response registerPRESERVEDNo owner responses admitted to date.
Evidence reconciliationPRESERVEDContradiction register empty because no evidence has been admitted.
Evidence IDClaim supportedSourceOwnerOwner authorityClassQualityPredicateDisposition
ER-01Aconex interface capabilityNot receivedDocument Control ManagerNOT VALIDATEDOPERATIONAL_CLOSURE_EVIDENCENONEBC-01EVIDENCE REQUIRED
ER-06IAM authentication and role modelNot receivedIAM OwnerNOT VALIDATEDOPERATIONAL_CLOSURE_EVIDENCENONEBC-02EVIDENCE REQUIRED
ER-07Decision-rights sourceNot receivedProject DirectorNOT VALIDATEDOPERATIONAL_CLOSURE_EVIDENCENONEBC-02EVIDENCE REQUIRED
ER-11Lifecycle / state governance ownershipNot receivedWork Control Process OwnerNOT VALIDATEDOPERATIONAL_CLOSURE_EVIDENCENONEBC-03EVIDENCE REQUIRED
ER-16Stewardship assignment (Location)Role defined onlyProject DirectorNOT VALIDATEDDESIGN_EVIDENCEINSUFFICIENTBC-04 (not satisfied)INCONCLUSIVE
ER-17Classification and retention policyNot receivedData Governance LeadNOT VALIDATEDOPERATIONAL_CLOSURE_EVIDENCENONEBC-05EVIDENCE REQUIRED

Admitted 0 · Confirmed 0 · Inconclusive 1 · Evidence required 5. No item reached OperationalClosureEvidence quality. Missing evidence is EVIDENCE_REQUIRED, not FAIL.

N–T. Operational validation domains

§19–26 · authority, source, IAM, signature, data governance, privacy, critical control, document

IDDomainItems requiredEvidence heldStatusBlockingNote
V-AUTHAuthority validation (§19)Accountable · Owner · Steward · Approver · Executor · Custodian · Escalation · DelegateRoles defined in design; no validated party for any material decisionUNVALIDATEDBLOCKINGOwnerNamed ≠ OwnerValidated. 6 of 8 roles unassigned.
V-SRCSource authority validation (§20)Document · WorkPackage / JobCard · Location · Identity · Competency · Training · FitnessDecision · Tool · Equipment · Restriction · CriticalControl · Permit · Isolation · Signature · Schedule0 of 15 objects have validated source authorityUNVALIDATEDBLOCKINGSystemConnected ≠ SystemAuthoritative preserved.
V-IAMIAM operational validation (§21)AuthenticationMechanism · IdentitySource · RoleAssignment · PermissionModel · DecisionRightSource · Delegation · Revocation · SessionValidity · StaleRoleBehaviour · OfflineAuthorityBehaviourMock IAM onlyUNVALIDATEDBLOCKINGMock IAM behaviour cannot close these requirements.
V-SIGDigital signature validation (§22)IdentityBinding · CredentialMechanism · TimestampMechanism · ObjectVersionBinding · IntegrityReference · Revocation · Retention · OfflineReconciliation (EXT-15) · EvidenceRequirementsDesign model only; no legal, security or PKI evidenceUNVALIDATEDBLOCKINGNo DigitalNotary / LegallyBinding / NonRepudiation claim made.
V-DGData governance validation (§23)DataOwner · DataSteward · Classification · Retention · Privacy · WriteAuthority · CorrectionAuthority · DataQualityResponsibility · HistoricalRecordCustodyNone admittedUNVALIDATEDBLOCKINGBC-05 remains open.
V-PRIPrivacy / personnel data (§24)FitnessDecisionFact · CompetencyDecisionFact · TrainingDecisionFactDesign confirms decision-fact-only consumption; owner approval absentPARTIALNON BLOCKINGData minimization designed in; approval still required (EXT-08).
V-CCCritical control governance (§25)CriticalControlSource · ControlOwner · VerificationAuthority · Validity · ChangeBehaviour · FieldConflictBehaviour · EvidenceRequirementCritical control remains SIMULATED; BC-06 Path A/B undecidedUNVALIDATEDBLOCKINGPrototype configuration cannot establish enterprise critical-control authority.
V-DOCDocument governance (§26)Document source · Revision governance · Supersession · Effective-date behaviour · Applicability authority · Document-status authority · Retention/custodyNoAutomaticRevisionElection preserved in design; no owner confirmationUNVALIDATEDBLOCKINGEXT-01 / EXT-02 open.
V-FLDField preconditions (§30)Device provisioning · Connectivity profile · Offline cache governance · Field support coverageNone admittedUNVALIDATEDBLOCKINGBC-08 remains open.

V. BC revalidation

§28 · status derived from current evidence, historical status is context only

BCTitleHistorical statusEvidence-derived statusEvidence basis
BC-01InterfacesREMAINS_OPENOPEN BLOCKINGNo interface capability evidence admitted (EXT-01/03/05/09).
BC-02IAMREMAINS_OPENOPEN BLOCKINGMock IAM only; V-IAM UNVALIDATED.
BC-03Lifecycle / state governanceREMAINS_OPENOPEN BLOCKINGState models designed and verified; governance ownership unevidenced.
BC-04Stewardship / change governanceREMAINS_OPENOPEN BLOCKINGLocation steward vacant (EXT-12 UNDER_VALIDATION).
BC-05Classification / retentionREMAINS_OPENOPEN BLOCKINGV-DG UNVALIDATED.
BC-06Critical controlREMAINS_OPENOPEN BLOCKINGPath A/B decision not taken; control SIMULATED.
BC-07Development / support ownershipREMAINS_OPENOPEN BLOCKINGNo corporate delivery organization accepted handover (EXT-16).
BC-08Field preconditionsREMAINS_OPENOPEN BLOCKINGV-FLD UNVALIDATED.
BC-09Prospective measurementREMAINS_OPEN (time-irreversible)OPEN BLOCKINGNo prospective BEFORE baseline started; protection ACTIVE.

W. BC-09 measurement readiness

§29 · time-irreversible; protection ACTIVE

Status
NOT READY
Protection
ACTIVE
Prospective baseline started
NO
Escalation
ESC-04 remains active.
ConstructDefinitionSource
ProcessTimeElapsed time of the governed operational processObserved operational measurement only
SystemTimeTime spent interacting with the systemInstrumented client telemetry (not yet enabled)
WaitingTimeTime blocked awaiting an external decision or factRestriction / HOLD timestamps
ManualHandlingTimeTime spent on manual paper or verbal coordinationProspective field observation
ReworkTimeTime consumed re-doing an invalidated stepReassessment event lineage
TimeSavedDifference between validated BEFORE and AFTER process timeRequires prospective BEFORE baseline
TimeReleasedCapacity released to other productive workRequires supervisor attribution
ProductiveTimeCapturedReleased time actually converted to productive workRequires independent confirmation
FinancialValueMonetary translation of confirmed productive timeRequires finance authority

Prohibited: RetrospectiveBaselineManufacturing · DoubleAttribution · SimulationToROIExtrapolation. Any pilot exposure before the BEFORE baseline starts permanently destroys the measurement opportunity.

X. G-PH6A — operational revalidation decision

§30–31 · HARD STOP after C2

Closure predicateSatisfiedObserved
CriticalOperationalBlockers = 0FALSE3 critical operational blockers open
HighUncontrolledOperationalBlockers = 0FALSE9 blocking BCs, controlled but unclosed
RequiredAuthorityValidatedFALSEV-AUTH UNVALIDATED
RequiredSourceAuthorityValidatedFALSEV-SRC UNVALIDATED (0/15 objects)
RequiredIAMBoundaryValidatedFALSEV-IAM UNVALIDATED
RequiredDataGovernanceValidatedFALSEV-DG UNVALIDATED
RequiredSignatureGovernanceValidatedFALSEV-SIG UNVALIDATED (incl. EXT-15)
RequiredCriticalControlGovernanceValidatedFALSEV-CC UNVALIDATED
RequiredFieldPreconditionsValidatedFALSEV-FLD UNVALIDATED
BC09ProspectiveMeasurementReadyFALSENOT_READY; protection ACTIVE
G-PH6A HOLDPHASE 6A HOLDCONTROLLED PILOT NOT AUTHORIZEDPILOT EXPOSURE PROHIBITED

HARD STOP after C2. Downstream stages C3–C5 are not executed and no synthetic pilot, production or handover results are generated.

Y–AD. Downstream stages not executed

§32–45 · no synthetic pilot, production or handover results generated

§ItemStatusReason
YControlled Pilot definition (PH6A-FPSO-PILOT-BASELINE-REV0)NOT CREATEDEntry condition G-PH6A = PASS not met. Creating a pilot baseline now would imply authorization that does not exist.
ZPilot evidence / acceptanceNOT AVAILABLENo pilot executed; PilotExposure = PROHIBITED.
AAProduction readiness assessmentNOT AUTHORIZEDRequires accepted real pilot evidence.
ABG-PH7 decisionNOT EVALUABLEPhase7 remains NO_GO; no simulated production GO permitted.
ACProduction release baselineNOT CREATEDRequires actual deployment authorization.
ADOperational handoverNOT AUTHORIZEDRequires competent operational acceptance that does not exist.

AE. Evidence maturity register

§46 · no silent promotion between levels

LevelEvidence classAchievedArtefacts
1DESIGN_EVIDENCEACHIEVEDIADA-REV1, SEAL-01, BXIA-REV0, FUNCTIONAL-BASELINE-REV1, IAD-REV2
2IMPLEMENTATION_EVIDENCEACHIEVEDPROTOTYPE-REV0
3SOFTWARE_VERIFICATION_EVIDENCEACHIEVEDICV-REV0, FVT-REV0
4SIMULATION_EVIDENCEACHIEVEDSCENARIO-BASELINE-REV0, E2E-DEMO-REV0, DAA-REV0
5OPERATIONAL_CLOSURE_EVIDENCENOT ACHIEVEDNOT_YET_ACQUIRED — 0 items admitted
6PILOT_EVIDENCENOT ACHIEVEDNOT_AVAILABLE
7PRODUCTION_EVIDENCENOT ACHIEVEDNOT_AVAILABLE

AF. Value capture register

§47

ConstructValueClaim status
SimulatedMeasurementPresent — scenario timings T0…T21VALUE HYPOTHESIS ONLY
ObservedOperationalMeasurementNoneNOT AVAILABLE
TimeSavedNot claimedREQUIRES PROSPECTIVE BASELINE
TimeReleasedNot claimedREQUIRES PROSPECTIVE BASELINE
ProductiveTimeCapturedNot claimedREQUIRES INDEPENDENT CONFIRMATION
FinancialValueNot claimedREQUIRES FINANCE AUTHORITY

NoDoubleCounting · NoSimulationAsActualBaseline · NoRetrospectiveBeforeFabrication

AG. Corporate decision register

§49 · bridge between engineering closure and organizational closure

IDDecision requiredAffected capabilityCompetent authorityEvidence requiredCurrent evidenceStatusSafe interim behaviourGate affected
CD-01Accept the corporate development handover package and name a delivery organizationAll (CAP-01…26)Corporate IT / Digital DeliveryHandover acceptance recordNoneOPENPackage remains READY_TO_ENGAGEBC-07 / G-PH6A
CD-02Designate the system of record for each of the 15 governed objectsCAP-03/07/12/17/18Process owners per objectObject-by-object owner confirmationNoneOPENAll objects treated as candidate sources; fail closedG-PH6A
CD-03Approve IAM integration pattern and decision-rights sourceCAP-20IAM Owner + Project DirectorIAM architecture + authority registerNoneOPENNo material decision without authenticated identity and resolved rightBC-02
CD-04Critical control Path A (real integration) or Path B (formal rescope)CAP-17Corporate ES&HDecision record with DecisionAuthority, Reason, PilotEvidenceLost, ResidualRisk, Phase7ImpactNoneOPENCritical control SIMULATED and not usable for releaseBC-06
CD-05Digital signature legal sufficiency and credential mechanismCAP-13/15Legal + Corporate SecurityLegal opinion + security approvalNoneOPENSignature captured as evidence only; no legal claimG-PH6A / G-PH7
CD-06Offline signature reconciliation authority (EXT-15)CAP-15Legal + Work Control Process OwnerSigned offline reconciliation ruleNoneOPENApplicability lost on version divergence; decision re-requiredG-PH6A
CD-07Data classification, retention and custody policy for readiness evidenceCAP-23Data Governance LeadApproved policyNoneOPENPrototype retains synthetic data onlyBC-05
CD-08Name the Location data steward and accept terms of referenceCAP-02Project DirectorAcceptance recordRole defined, party vacantOPENManual verification of location changesBC-04
CD-09Authorize the start of prospective BEFORE measurementCAP-25Project DirectorMeasurement start recordNoneOPENBC09Protection ACTIVE; no pilot exposureBC-09
CD-10Issue non-functional requirements (SLA/SLO/RTO/RPO/retention)CAP-26Service Owner (unassigned)Approved NFR specificationNoneOPENREQUIREMENT_REQUIRED_FROM_COMPETENT_OWNER; nothing inventedG-PH7
CD-11Cybersecurity review and disposition of the target patternAll production capabilitiesCorporate CybersecuritySecurity approval recordNoneOPENNo production environment provisionedG-PH7
CD-12Resolve ADR-03 authoritative restriction systemCAP-19Project Controls + ES&HADR decision recordNoneOPENRestrictions remain non-compensable blockersG-PH6A

AH. Operational closure dashboard

§50 · no compensated aggregate scoring

TotalExternalDependencies
18
Closed
0
UnderValidation
1
EvidenceRequired
17
Contradicted
0
BlockingBCs
9
AuthorityValidation
UNVALIDATED
SourceAuthorityValidation
UNVALIDATED
IAMValidation
UNVALIDATED
SignatureValidation
UNVALIDATED
DataGovernance
UNVALIDATED
CriticalControlGovernance
UNVALIDATED
BC09MeasurementReadiness
NOT READY
Phase6AStatus
HOLD

Next authorized action

Engage the corporate development organization with PH6A-CORPORATE-DEVELOPMENT-HANDOVER-REV0 and continue acquiring OperationalClosureEvidence against the 9 blocking BCs and 18 external dependencies. No pilot exposure.

NO_COMPENSATED_AGGREGATE_SCORING — a single blocking condition is displayed as blocking regardless of overall progress.

AI. Master gate register

§48 · historical decisions preserved, never overwritten

GateTitleDecisionMacroRow
G-FPSO-01Architecture Impact AssessmentPASSPH6A-FPSO-AIA-REV0HISTORICAL
G-FPSO-02Functional Contract DefinitionPASSPH6A-FPSO-FCD-REV0HISTORICAL
G-FPSO-03Contract Assurance & Baseline FreezePASSPH6A-FPSO-FCA-REV0HISTORICAL
G-FPSO-04Design-to-Contract ConformancePASSPH6A-FPSO-IAD-REV2HISTORICAL
G-FPSO-04BBechtelized Application ConformancePASSPH6A-FPSO-BAC-REV0HISTORICAL
G-FPSO-05Implementation ConformancePASSPH6A-FPSO-ICV-REV0HISTORICAL
G-FPSO-06Scenario Baseline FreezePASSPH6A-FPSO-MPB-REV0HISTORICAL
G-FPSO-07Demonstrator AcceptancePASSPH6A-FPSO-DAA-REV0HISTORICAL
G-FPSO-08Corporate Development Handover ReadinessPASSPH6A-FPSO-MPC-REV0APPENDED
G-PH6APhase 6A Operational RevalidationHOLDPH6A-FPSO-MPC-REV0APPENDED
G-PILOTControlled Pilot GateNOT EVALUABLEPH6A-FPSO-MPC-REV0APPENDED
G-PH7Production ReadinessNOT EVALUABLEPH6A-FPSO-MPC-REV0APPENDED
G-HANDOVEROperational Handover GateNOT EVALUABLEPH6A-FPSO-MPC-REV0APPENDED

AJ. Open findings & residual risk

§51 · 6 findings · 0 critical uncontrolled

F-MPC-01HIGHC2Source authority
Current architectural condition
Every governed object has a candidate system but none has validated source authority.
Structural exposure
The decision layer would consume facts whose semantic authority is unproven, so a correct computation could still rest on a non-authoritative fact.
Downstream consequence
Any pilot decision would be unattributable; audit reconstruction would terminate at an unauthorised source.
Required decision
Object-by-object system-of-record designation (CD-02).
Competent authority
Process owner per object
Evidence of closure
Written designation per object with write-authority statement
Residual risk
Contained today because no live integration exists and PilotExposure is PROHIBITED.
F-MPC-02HIGHC2Authority / IAM
Current architectural condition
Decision rights exist as a model; 6 of 8 material roles are unassigned.
Structural exposure
The system is designed to consume authority it cannot currently obtain, so every material decision path resolves to UNRESOLVED and fails closed.
Downstream consequence
A pilot would produce continuous fail-closed states, which would be misread as product defects rather than organizational gaps.
Required decision
Authority register issuance and IAM pattern approval (CD-03).
Competent authority
Project Director + IAM Owner
Evidence of closure
Signed decision-rights register with effective periods
Residual risk
Contained by fail-closed default; no bypass exists.
F-MPC-03CRITICALC2Critical control governance
Current architectural condition
Critical control status remains SIMULATED with no Path A/B decision.
Structural exposure
The only non-compensable ES&H gate in the model is fed by a simulated fact, which is precisely the failure mode the no-compensation rule exists to prevent.
Downstream consequence
Any pilot release decision would be safety-unsupported; Phase 7 cannot be reached.
Required decision
BC-06 Path A or formal Path B rescope (CD-04).
Competent authority
Corporate ES&H
Evidence of closure
Integration evidence or recorded rescope with residual risk
Residual risk
Contained only because PilotExposure is PROHIBITED. This is the single condition most likely to be wrongly closed for convenience.
F-MPC-04HIGHC2Signature governance
Current architectural condition
Signature evidence is captured and correctly separated from applicability, but no credential, timestamp or legal mechanism is evidenced; EXT-15 remains open.
Structural exposure
A structurally correct signature model without corporate credential binding produces records that look authoritative but carry no verifiable identity binding.
Downstream consequence
Evidence produced in a pilot could not be relied upon after the fact.
Required decision
Credential mechanism, legal sufficiency, offline reconciliation authority (CD-05, CD-06).
Competent authority
Legal + Corporate Security + Work Control Process Owner
Evidence of closure
Legal opinion, security approval, signed offline reconciliation rule
Residual risk
Contained by making no legal claim and by losing applicability on version divergence.
F-MPC-05CRITICALC2Measurement integrity (BC-09)
Current architectural condition
No prospective BEFORE baseline has started while a demonstrable prototype exists.
Structural exposure
The measurement opportunity is time-irreversible: the first exposure of the new way of working destroys the ability to measure the old one.
Downstream consequence
Value claims would become permanently unfalsifiable and Phase 7 benefit assessment would rest on simulation.
Required decision
Authorize prospective measurement start before any exposure (CD-09).
Competent authority
Project Director
Evidence of closure
Measurement start record with collection underway
Residual risk
Contained by BC09Protection ACTIVE and ESC-04; risk increases with every day of stakeholder demonstration pressure.
F-MPC-06MEDIUMC1Industrialization ownership
Current architectural condition
A complete handover package exists with no named receiving corporate development organization.
Structural exposure
An unowned handover package decays: baselines freeze while the enterprise context moves, and semantic drift enters through reinterpretation rather than change control.
Downstream consequence
BC-07 cannot close and no production implementation can begin.
Required decision
Name and engage the delivery organization (CD-01).
Competent authority
Corporate IT / Digital Delivery
Evidence of closure
Handover acceptance record
Residual risk
Contained by configuration seal and frozen baselines, but decay risk grows with elapsed time.

Macro C discipline regression

20/20 PASS

IDStatementResultBasis
MPC-R01MacroPromptC authorization independently reconstructed, not assumedPASS5/5 authorization checks recomputed from MPB exports.
MPC-R02No implementation derived from a superseded baselinePASS3 superseded baselines flagged historical only.
MPC-R03Operational boundary preserved unchanged by C1PASSBoundary states unmodified outside gates.
MPC-R04No capability classified PRODUCTION_READYPASS26 capabilities classified across governed classes only.
MPC-R05No external API or integration capability fabricatedPASSAll 10 interfaces recorded as candidate with EVIDENCE_REQUIRED / UNDER_VALIDATION.
MPC-R06EXT-15 carried forward and visible in all mandated registersPASSPresent in handover, revalidation, signature and offline models.
MPC-R07External dependency IDs never renumberedPASSEXT-01…15 preserved; EXT-16…18 newly assigned.
MPC-R08Dependency count independently reconstructed, not forced to 15PASS15 carried forward + 3 new corporate-scope dependencies.
MPC-R09Traceability chain complete with zero breaksPASS12 chains architecture → acceptance criterion.
MPC-R10No evidence item promoted between maturity classesPASSLevels 5–7 unachieved.
MPC-R11Missing evidence recorded as EVIDENCE_REQUIRED, never FAIL or PASSPASS5 EVIDENCE_REQUIRED, 1 INCONCLUSIVE, 0 admitted.
MPC-R12BC status derived from current evidence, not inherited statusPASSEach BC re-derived from admitted evidence (none).
MPC-R13BC09 protection preserved; no retrospective baseline manufacturedPASS9 measurement constructs defined; no value claimed.
MPC-R14No synthetic pilot, production or handover results generated after HOLDPASSC3–C5 not executed; entry conditions unmet.
MPC-R15Dashboard uses no compensated aggregate scoringPASSBlocking conditions surfaced individually; no composite score.
MPC-R16Historical gate decisions preserved and never overwrittenPASS8 historical rows retained; 5 new rows appended.
MPC-R17Equivalence predicate stated for corporate reimplementationPASS5-term antecedent required.
MPC-R18Temporal coherence carried into acceptance criteriaPASSCIAC-03/04/05 enforce XR-TEMP-01.
MPC-R19No unsupported legal / notary / non-repudiation claimPASSV-SIG explicitly withholds all three claims.
MPC-R20Macro status is a specific controlled status, not generic ACCEPTEDPASSStatus = CORPORATE_HANDOVER_READY_OPERATIONAL_EVIDENCE_PENDING.

§56 Hard stop conditions

ConditionApplies
CorporateHandoverIncompleteFALSE
OperationalClosureEvidenceInsufficientTRUE
CriticalOperationalBlocker > 0TRUE
HighUncontrolledOperationalBlocker > 0FALSE
RequiredAuthorityUnvalidatedTRUE
RequiredSourceAuthorityUnvalidatedTRUE
RequiredIAMUnvalidatedTRUE
RequiredSignatureGovernanceUnvalidatedTRUE
RequiredDataGovernanceUnvalidatedTRUE
RequiredCriticalControlGovernanceUnvalidatedTRUE
BC09MeasurementBaselineNotReadyTRUE

Downstream progression stopped. No bypass via prototype, mock or simulation evidence, management preference or AI inference.

§55 Required final response

MACRO_PROMPT_C
CORPORATE_HANDOVER_READY_OPERATIONAL_EVIDENCE_PENDING
MacroID
PH6A-FPSO-MPC-REV0
CorporateDevelopmentHandover
READY
CorporateDevelopmentHandoverBaseline
PH6A-CORPORATE-DEVELOPMENT-HANDOVER-REV0
G-FPSO-08
PASS
OperationalClosureEvidenceStatus
NOT_YET_ACQUIRED / INCOMPLETE — 0 items admitted
ExternalDependencyCount
18
ExternalDependenciesClosed
0
ExternalDependenciesUnderValidation
1
ExternalDependenciesOpen
17
BlockingBCCount
9
AuthorityValidationStatus
UNVALIDATED
SourceAuthorityValidationStatus
UNVALIDATED
IAMValidationStatus
UNVALIDATED
DigitalSignatureValidationStatus
UNVALIDATED
DataGovernanceValidationStatus
UNVALIDATED
CriticalControlValidationStatus
UNVALIDATED
BC09MeasurementReadiness
NOT_READY
G-PH6A
HOLD
Phase6A
HOLD
ControlledPilot
NOT_AUTHORIZED
ProductionReadiness
NOT_AUTHORIZED
Phase7
NO_GO
OperationalHandover
NOT_AUTHORIZED
EvidenceClassHighestAchieved
SIMULATION_EVIDENCE
NextAuthorizedAction
Engage the corporate development organization with PH6A-CORPORATE-DEVELOPMENT-HANDOVER-REV0 and continue acquiring OperationalClosureEvidence against the 9 blocking BCs and 18 external dependencies. No pilot exposure.