Scenario 02 — ES&H Ready / Client Release Missing
Pipe rack spool installation — Line 2140-PL-12
Mechanical installation with mobile crane lift
Operational
HOLDExecution
NOT STARTEDTechnology
ONLINEproject Id
PRJ-4820
contract Id
CTR-EPCM-02
area Id
ARE-200
facility Id
FAC-CONC
system Id
SYS-2140
subsystem Id
SUB-2140-02
wbs Id
WBS-2.4.2
activity Id
A-1202
work Package Id
WP-1002
swpp Id
SWPP-302
location Id
LOC-200-EL12
equipment Id
EQ-2140-MCC1
discipline Id
DIS-ELE
shift Id
SHF-DAY-A
functional Owner Id
ROL-ENGM
construction Owner Id
ROL-SUPT
Determinants of the integrated state
Every determinant is listed independently. None was averaged, weighted or offset.
- HOLDClient Release ReadinessClient release letter CRL-0442 not issued; tie-in window not confirmed.Owner: Client Interface ManagerNON-COMPENSABLE
- HOLDRST-2001Client release pending for tie-in windowOwner: Client Interface ManagerNON-COMPENSABLE
Decision context
Every ES&H gate is satisfied. Client Release is outstanding, which is non-compensable, so the integrated state is HOLD and ownership stays with the Client Interface Manager.
Phase
Construction
Planned start
2026-08-30 07:00:00Z
Discipline
Mechanical
Area
Area 200 — Process
Required approval role
Permit Authorizer — Area 200 / Day A
Approver
PER-2001 (ROL-PA)
Approver available
Yes
Delegate
None in scope
External object references
Source systems own their records. This layer owns only the integrated decision context.
| Source system | Object | ID | Source status | Revision | Last verified | Business owner | Data steward | Write authority | Mode | Reconciliation |
|---|---|---|---|---|---|---|---|---|---|---|
| Primavera P6 | Activity | A-1202 | APPROVED | Baseline BL-2026-08 | 2026-08-29 23:10:00Z | Project Controls Manager | Planning Lead | Primavera P6 | READ | IN SYNC |