Scenario 07 — Offline Field Operation
Grounding grid continuity testing — Area 100
Field testing with offline evidence capture
Operational
READYExecution
CONTINUETechnology
OFFLINEproject Id
PRJ-4820
contract Id
CTR-EPCM-02
area Id
ARE-200
facility Id
FAC-CONC
system Id
SYS-2140
subsystem Id
SUB-2140-02
wbs Id
WBS-2.4.7
activity Id
A-1207
work Package Id
WP-1007
swpp Id
SWPP-307
location Id
LOC-200-EL12
equipment Id
EQ-2140-MCC1
discipline Id
DIS-ELE
shift Id
SHF-DAY-A
functional Owner Id
ROL-ENGM
construction Owner Id
ROL-SUPT
No open determinants. All mandatory conditions verified against their authoritative sources.
Decision context
The crew is operating outside coverage on the approved offline package. Local evidence capture is permitted and queued as immutable events.
Phase
Precommissioning
Planned start
2026-08-30 07:00:00Z
Discipline
Electrical
Area
Area 100 — Intake
Required approval role
Permit Authorizer — Area 200 / Day A
Approver
PER-2001 (ROL-PA)
Approver available
Yes
Delegate
None in scope
External object references
Source systems own their records. This layer owns only the integrated decision context.
| Source system | Object | ID | Source status | Revision | Last verified | Business owner | Data steward | Write authority | Mode | Reconciliation |
|---|---|---|---|---|---|---|---|---|---|---|
| Primavera P6 | Activity | A-1207 | APPROVED | Baseline BL-2026-08 | 2026-08-29 23:10:00Z | Project Controls Manager | Planning Lead | Primavera P6 | READ | STALE |