Scenario 10 — Q4 Sanction to Test
Pump P-2170 sanction to test — motor solo run
Energisation and solo run under Sanction to Test
Operational
CONDITIONALExecution
NOT STARTEDTechnology
ONLINEproject Id
PRJ-4820
contract Id
CTR-EPCM-02
area Id
ARE-200
facility Id
FAC-CONC
system Id
SYS-2140
subsystem Id
SUB-2140-02
wbs Id
WBS-2.4.10
activity Id
A-1210
work Package Id
WP-1010
swpp Id
SWPP-310
location Id
LOC-200-EL12
equipment Id
EQ-2140-MCC1
discipline Id
DIS-ELE
shift Id
SHF-DAY-A
functional Owner Id
ROL-ENGM
construction Owner Id
ROL-SUPT
Determinants of the integrated state
Every determinant is listed independently. None was averaged, weighted or offset.
- CONDITIONALG3 Operational & CompetencySIMOPS interface with WP-1011 requires zone coordination before energisation.Owner: General ForemanNON-COMPENSABLE
Decision context
An approved Sanction to Test links isolation, equipment and work package. Adjacent construction work in the same zone becomes CONDITIONAL under SIMOPS.
Phase
Commissioning
Planned start
2026-08-30 07:00:00Z
Discipline
Electrical
Area
Area 200 — Process
Required approval role
Permit Authorizer — Area 200 / Day A
Approver
PER-2001 (ROL-PA)
Approver available
Yes
Delegate
None in scope
External object references
Source systems own their records. This layer owns only the integrated decision context.
| Source system | Object | ID | Source status | Revision | Last verified | Business owner | Data steward | Write authority | Mode | Reconciliation |
|---|---|---|---|---|---|---|---|---|---|---|
| Primavera P6 | Activity | A-1210 | APPROVED | Baseline BL-2026-08 | 2026-08-29 23:10:00Z | Project Controls Manager | Planning Lead | Primavera P6 | READ | IN SYNC |
| Q4 / Entity Desk | Sanction to Test | Q4-STT-60110 | APPROVED | v2 | 2026-08-29 23:10:00Z | Commissioning Manager | Work Control | Q4 / Entity Desk | READ/EVENT | IN SYNC |