Phase 1 prototype · Phase 2A corrective verification · SYNTHETIC DEMONSTRATION DATA
Integrated Preventive Readiness
Acting role — demonstration device only, not an authorization mechanism
Superintendent: What will be ready across my area, and what must be resequenced?
JC-7702 · Electrical
MCC-3100-B feeder termination and loop power-up
Location
Window
2026-09-02 06:00 → 2026-09-02 16:00
Crew
5 persons
Required by
2026-09-02 05:30
Primary blocker
Concurrent energised work while CV-07 isolation boundary is shared (CUM-1) · Owner: Isolation AuthorityEnabling conditions
2 mandatory condition(s) not satisfiedEC-11 · MANDATORY Arc-flash PPE certification current for all crew PEOPLE · Source: People system (SoR) · Owner: Training Coordinator · Valid until 2026-09-02 12:00 · Required by 2026-09-02 05:00 | EXPIRING |
EC-12 · MANDATORY Single-line diagram ELE-3100-221 rev F pinned DOCUMENT · Source: Aconex (SoR) · Owner: Document Controller | SATISFIED |
EC-13 · MANDATORY Live-work justification approved DOCUMENT · Source: Q4 · Owner: Electrical Authority | SATISFIED |
EC-14 · MANDATORY Test instruments calibrated TOOLS · Source: Calibration register · Owner: Functional Owner — Electrical · Valid until 2026-10-01 00:00 | SATISFIED |
EC-15 · MANDATORY Boundary segregation from ISO-CV07-A confirmed by Isolation Authority CONTROL · Source: Q4 isolation register · Owner: Isolation Authority · Required by 2026-09-02 05:30 | UNVERIFIABLE |
Preventive package
applicability composed by PACE — proposal is not validation- PP-11HUMAN CONFIRMEDEVIDENCE GRADEEnergised-work barrier and attendantProposed by PACE (rule PKG-LIVE-01) · Live terminations within 6 m of access route.
- ConfirmedBy
- ES&H — M. Vera
- ConfirmedRole
- GOVERNED_POSITION (pre-session record)
- ConfirmedAt
- 2026-09-01 17:05
- ObjectVersion
- package v2 · context v7
- ConfirmationContext
- JC-7702 · 3100-CONC-CV07-TT01 · preventive package confirmation
- EvidenceRef
- EV-BASE-PP-11
- PP-12SYSTEM PROPOSEDCross-discipline isolation briefing with mechanical crewProposed by PACE (rule PKG-SIMOPS-03) · Shared isolation boundary detected in the concurrent work set.Acting identity: Area Superintendent — Concentrator (PSN-2210)
IPERC Continuo
predicted context is never displayed as validated- IP-11PREDICTEDAWAITING FIELD CONFIRMATIONArc flash during terminationControl: LCR-05
- IP-12PREDICTEDAWAITING FIELD CONFIRMATIONUnexpected back-feed from UPS circuitControl: LCR-05
Work control — PETAR / PTW routing
no auto-authorization anywhere in this flow- PTW-99205PTWAUTHORIZEDREADYQ4 state: Authorized · Next actor: — · Auto-authorized: falseGENERATEDIN_REVIEWVALIDATEDAUTHORIZED
- JHA-3320JHABLOCKEDUNMAPPED STATEQ4 state: Locked · Next actor: Governance Administrator (CA-03) · Auto-authorized: falseGENERATEDIN_REVIEWVALIDATEDAUTHORIZED
Risk decomposition
activity · location · SIMOPS interaction risks are never mergedActivity risk
Arc flash during termination
Unexpected back-feed from UPS circuit
Location risk
LCR-02 — Working at height
LCR-05 — Energy isolation
LCR-07 — Lifting operations
SIMOPS interaction risk
Concurrent energised work while CV-07 isolation boundary is shared (CUM-1)
Authorization
application access is not operational authorityLife critical controls
LCR-05 Energy isolation
Energy states
ELECTRICAL_LIVE
Isolation boundaries
ISO-CV07-A
Exclusion zone
6 m
Authorization is withheld while any mandatory condition is unsatisfied or the location SIMOPS verdict is STOP. The prototype exposes no path to release under these states.
Changes and reassessment
selective, bounded reassessment (TC-11)- 2026-09-01 11:30Q4 returned state 'Locked' for JHA-3320Impact: State not in the governed mapping table — fails closed · Reassessment: Blocked pending CA-03 / ADR mapping decision
Continuity context received
Inherit context — never inherit authorization.- INHERITEDLocation height risk context LCR-02
- INHERITEDAccess route and barricade plan
- INHERITEDEquipment register entry CV-07 (as-left mechanical state)
- INHERITEDLesson LL-2211
- NOT INHERITEDPTW-99180 (mechanical)
- NOT INHERITEDIsolation certificate ISO-CV07-M
Prototype behaviour note
Phase 2A: confirmations carry ConfirmedBy / ConfirmedRole / ConfirmedAt / ConfirmationContext / ObjectVersion / EvidenceRef and are reconstructable in the Authority & Evidence console. Session-scoped store; no persistence beyond the session.