PizarraContexto de trabajoDocumentos y registrosControles críticosRegistrosPreparaciónCondiciones bloqueantesAutorización
Aseguramiento / Técnico
Phase 1 prototype · Phase 2A corrective verification · SYNTHETIC DEMONSTRATION DATA

Integrated Preventive Readiness

Hold point — Phase 3 not authorized
Acting role — demonstration device only, not an authorization mechanism

Superintendent: What will be ready across my area, and what must be resequenced?

Shift / lookahead readiness

All disciplines in the governed location · demonstration clock 2026-09-02

Job CardLocationDisciplineCurrentForecastSIMOPSPrimary blockerOwnerRequired byOperational state
JC-7701
CV-07 head pulley bearing replacement
3100-CONC-CV07-TT01MechanicalSTOPSTOP
Location-level cumulative SIMOPS STOP is non-compensable and persists across the window.
STOPSIMOPS CUM-3 — lifting envelope overlaps occupied grating (RST-441)Shift SIMOPS Coordinator2026-09-02 05:00PREPARING
JC-7702
MCC-3100-B feeder termination and loop power-up
3100-CONC-CV07-TT01ElectricalCONDITIONALHOLD
Arc-flash PPE certification for two crew members expires at 12:00 inside the execution window.
STOPConcurrent energised work while CV-07 isolation boundary is shared (CUM-1)Isolation Authority2026-09-02 05:30AUTHORIZED
JC-7703
CV-07 belt-drift and speed instrumentation loop check
3100-CONC-CV07-TT01InstrumentationHOLDCONDITIONAL
Becomes CONDITIONAL only if the mechanical lift is resequenced out of the overlap window.
STOPRequirement REQ-INST-114 has CLASSIFICATION_UNRESOLVED — fails closedFunctional Owner — Instrumentation2026-09-02 08:00PLANNED

Verdicts are derived by rule. No aggregation, weighting or averaging is applied; a mandatory failure cannot be offset by satisfied conditions elsewhere.

Forecast horizon

Gaps that will occur inside the planned execution window

2026-09-02 12:00EXPIRYArc-flash PPE certification (2 persons)JC-7702 CONDITIONAL → HOLDOwner: Training Coordinator
2026-09-02 12:00EXPIRYRigger competency (1 person)JC-7701 lift crew below minimumOwner: Training Coordinator
2026-09-02 13:00ENVIRONMENTWind gust forecast 21 m/sLifting suspended; EC-04 breach window 13:00–17:00Owner: Shift Superintendent
2026-09-03 06:00EXPIRYIsolation certificate ISO-CV07-A validity endExtension or re-isolation requiredOwner: Isolation Authority