Phase 1 prototype · Phase 2A corrective verification · SYNTHETIC DEMONSTRATION DATA
Integrated Preventive Readiness
Acting role — demonstration device only, not an authorization mechanism
Superintendent: What will be ready across my area, and what must be resequenced?
JC-7703 · Instrumentation
CV-07 belt-drift and speed instrumentation loop check
Location
Window
2026-09-02 10:00 → 2026-09-02 20:00
Crew
4 persons
Required by
2026-09-02 08:00
Primary blocker
Requirement REQ-INST-114 has CLASSIFICATION_UNRESOLVED — fails closed · Owner: Functional Owner — InstrumentationEnabling conditions
1 mandatory condition(s) not satisfiedEC-21 · MANDATORY Loop folder INS-CV07-LP12 rev B pinned DOCUMENT · Source: Smart Completions · Owner: Completions Engineer | SATISFIED |
EC-22 · MANDATORY REQ-INST-114 criticality classified by Functional Owner CONTROL · Source: Requirement register · Owner: Functional Owner — Instrumentation · Required by 2026-09-02 08:00 | UNVERIFIABLE |
EC-23 · MANDATORY Working-at-height context inherited from parent location and revalidated CONTROL · Source: Canonical Location Register (inherited, applicability checked) · Owner: Readiness Governance Lead | SATISFIED |
EC-24 · MANDATORY Calibrated loop tester assigned TOOLS · Source: Calibration register · Owner: Functional Owner — Instrumentation · Valid until 2026-12-01 00:00 | SATISFIED |
Preventive package
applicability composed by PACE — proposal is not validation- PP-21SYSTEM PROPOSEDHeight access plan with fall-restraint anchorage registerProposed by PACE (rule PKG-HEIGHT-02) · Inherited location height context (LCR-02) with applicability confirmed.Acting identity: Area Superintendent — Concentrator (PSN-2210)
IPERC Continuo
predicted context is never displayed as validated- IP-21PREDICTEDAWAITING FIELD CONFIRMATIONFall from grating edgeControl: LCR-02
- IP-22PREDICTEDAWAITING FIELD CONFIRMATIONInteraction with concurrent lifting activityControl: LCR-07
Work control — PETAR / PTW routing
no auto-authorization anywhere in this flow- PETAR-4415PETARGENERATEDHOLDQ4 state: Draft · Next actor: ES&H (review) · Auto-authorized: falseGENERATEDIN_REVIEWVALIDATEDAUTHORIZED
Risk decomposition
activity · location · SIMOPS interaction risks are never mergedActivity risk
Fall from grating edge
Interaction with concurrent lifting activity
Location risk
LCR-02 — Working at height
LCR-05 — Energy isolation
LCR-07 — Lifting operations
SIMOPS interaction risk
Requirement REQ-INST-114 has CLASSIFICATION_UNRESOLVED — fails closed
Authorization
application access is not operational authorityLife critical controls
LCR-02 Working at height
Energy states
ELECTRICAL_LIVE
Isolation boundaries
—
Exclusion zone
4 m
Authorization is withheld while any mandatory condition is unsatisfied or the location SIMOPS verdict is STOP. The prototype exposes no path to release under these states.
Changes and reassessment
selective, bounded reassessment (TC-11)- 2026-09-01 09:10REQ-INST-114 introduced without governed classificationImpact: PACE cannot determine applicability · Reassessment: Fails closed — no default criticality assumed
Continuity context received
Inherit context — never inherit authorization.- INHERITEDLocation height risk context LCR-02
- INHERITEDAccess route and barricade plan
- INHERITEDEquipment register entry CV-07 (as-left mechanical state)
- INHERITEDLesson LL-2211
- NOT INHERITEDPTW-99180 (mechanical)
- NOT INHERITEDIsolation certificate ISO-CV07-M
Prototype behaviour note
Phase 2A: confirmations carry ConfirmedBy / ConfirmedRole / ConfirmedAt / ConfirmationContext / ObjectVersion / EvidenceRef and are reconstructable in the Authority & Evidence console. Session-scoped store; no persistence beyond the session.